Reviewing and controlling process changes

Approx. 65–100 minutes

Independent SHAREhub process-safety awareness. Selected learning maps to a numbered process-safety syllabus topic; this is not the NEBOSH qualification, approved provision, specialist design instruction or work authorisation. GB guidance is distinguished from corresponding NI requirements; establish applicability for the actual jurisdiction and establishment.

This reader supplies the complete teaching. Use the interactive LMS course for assessed activities, saved progress and completion.

LESSON 1

Recognise more than hardware change

Identify changes to people, materials and procedures.

Process operators monitoring equipment from a UK industrial control room
Existing SHAREhub photographic illustration. The written fictional case supplies the condition and decision evidence.

Recognise more than hardware change

A change can alter risk without moving a pipe. A different feed composition, operating sequence, staffing arrangement or software setting can affect the basis on which controls were selected. Consider what the proposal changes in the process, not merely its purchase description.

Routine work and proposed changes need a clear boundary. Use the site’s screening arrangements to decide what review is necessary. Awareness means recognising a possible trigger and supplying the facts; it does not authorise the learner to declare a change insignificant because it is inexpensive or short-lived.

Which changes need screening?

Screen any change that could alter hazardous inventory, process conditions, equipment, software, procedure, organisation or emergency assumptions. A like-for-like claim must be verified, not assumed.

Examples include alternative materials or gasket, temporary hose, new contractor, revised maintenance interval, control-logic update, alarm setting, utility tie-in, new operating limit, staffing reduction or altered emergency route. Consider cumulative and simultaneous changes. Some routine replacements may pass a documented like-for-like screen; if specification or function differs, send them through full review. HSE COMAH plant modification and change procedures and HSE organisational change and major accident hazards.

Changes and hidden process-safety effects
Change type Example Potential effect
Plant or material Alternative seal or substance grade. Compatibility, containment or reaction differs.Sources: HSE COMAH plant modification and change procedures; HSE organisational change and major accident hazards
Control system Trip set point or software logic. Safety function or independence changes.Sources: HSE COMAH plant modification and change procedures; HSE organisational change and major accident hazards
Procedure New start-up sequence. Different abnormal state or operator response.Sources: HSE COMAH plant modification and change procedures; HSE organisational change and major accident hazards
People and organisation Reduced night engineering cover. Delayed defect response or lost technical authority.Sources: HSE COMAH plant modification and change procedures; HSE organisational change and major accident hazards
Temporary or emergency Bypass or provisional hose. Unreviewed load, inventory or expiry risk.Sources: HSE COMAH plant modification and change procedures; HSE organisational change and major accident hazards

Applied case

Fictional exercise: A supplier proposes a different feed grade under the existing product name.

Beyond hardware

People, procedures and materials can change dependencies.

Screening

Review the proposal before deciding its significance.

Test your decision

What should happen?

  1. Treat the unchanged name as proof of equivalence.
  2. Assume every feed change is prohibited.
  3. Screen the actual composition and process implications through the change process.
Compare the explanation

Screen the actual composition and process implications through the change process.

The actual changed characteristics matter.

Open this interactive lesson →

LESSON 2

Test a like-for-like claim

Examine equivalence against function and conditions.

Process operators monitoring equipment from a UK industrial control room. Photorealistic illustration.
Photorealistic illustrative UK workplace scene. Review checks: Avoid / redesign: Engineering assesses removing the transfer step or redesigning the process so the hazardous operation is unnecessary. Control the task: Competent designers specify required containment, relief or protective control changes and maintainable isolation/access for the actual changed duty. Verify before release: Verify that the harm route has been removed rather than transferred.

Test a like-for-like claim

A replacement may look identical yet have different materials, performance or failure behaviour. “Like for like” needs evidence appropriate to the function and operating conditions. The catalogue description is only one input.

Identify the current requirement and compare the proposed item against it through competent review. If information is missing, retain that uncertainty. Do not assume a mismatch proves failure, but do not use absence of evidence as confirmation of equivalence. The screening decision should remain traceable for later work and maintenance.

A familiar name does not prove like-for-like replacement

A replacement must be compared with the applicable design and operating basis, including its interfaces and failure behaviour.

Fictional learning example

Separate the evidence from the decision
Part of the pictureWhat the example establishes
ProposalA replacement valve has the same nominal connection size.
UnconfirmedMaterials, flow characteristics and failure position have not been compared.
Open interfaceThe actuator and protective function may respond differently on utility loss.

Pause and decide: Is the matching connection size enough to bypass change review?

Compare the reasoning

No. Use the site change-screening route and compare the features relevant to the actual duty. A genuine like-for-like decision needs evidence. If the change is temporary, keep its expiry, owner, restrictions and restoration plan visible through handover and pre-start review.

What is the first MOC screening decision?

Define the existing and proposed state, the reason, affected assets and duration. Decide whether credible scenarios or credited controls could change, and record the basis.

Use current drawings, process information, operating limits, barrier register and field walk. Identify connected equipment, neighbouring work and affected personnel. A “minor” label should describe the result of competent screening, not bypass it. If information is missing, hold the alteration until the boundary is understood. HSE COMAH plant modification and change procedures.

Applied case

Fictional exercise: A replacement seal has the same dimensions; chemical compatibility evidence is missing.

Fit

Dimensions concern physical compatibility.

Function

Material and service requirements need their own basis.

Test your decision

What does the dimensional match establish?

  1. Certain immediate failure.
  2. Fit information only; functional equivalence remains unresolved.
  3. Complete process suitability.
Compare the explanation

Fit information only; functional equivalence remains unresolved.

One matching attribute cannot establish all required characteristics.

Open this interactive lesson →

LESSON 3

Start from the current design basis

Identify dependencies before judging the proposal.

Process operators monitoring equipment from a UK industrial control room. Photorealistic illustration.
Photorealistic illustrative UK workplace scene. Review checks: Change at source: Engineering assesses removing the transfer step or redesigning the process so the hazardous operation is unnecessary. Make it observable: Verify that the harm route has been removed rather than transferred. Keep useful evidence: Retain screen, hazard study, technical approvals, as-built check, pressure/leak and function tests, procedure, competence, temporary expiry and final removal record.

Start from the current design basis

A review needs an accurate baseline: current configuration, process information, limits, protective functions and interfaces. Reviewing an obsolete drawing can miss the connection the change will actually affect.

Define the proposal and its boundary clearly enough to examine effects upstream, downstream and on utilities or emergency response. Include normal and foreseeable abnormal conditions. A list of drawing numbers does not demonstrate that the drawings represent the plant. Obtain the appropriate competent contributions and record assumptions that still need confirmation.

What must the hazard review examine?

Examine new initiating events, changed consequences, barrier dependencies, human tasks, abnormal modes and off-site effects. Scale the method to the hazard and complexity.

A focused multidisciplinary review may be enough for a bounded change; a complex modification may need a formal hazard and operability or other study. Test normal, start-up, shutdown, maintenance, utility failure and emergency conditions. Challenge assumptions about relief, isolation, ignition, common-cause failure, operator time and contractor interfaces. Record actions, owners and evidence needed before start. HSE COMAH plant modification and change procedures and HSE COMAH control systems.

Applied case

Fictional exercise: The proposed supply change is reviewed against a superseded diagram.

Baseline

What is installed and controlled now?

Boundary

Which connected functions could the proposal affect?

Test your decision

What must be resolved?

  1. The current configuration and affected dependencies before the review conclusion.
  2. Only the diagram’s file size.
  3. A claim that the supply must already be defective.
Compare the explanation

The current configuration and affected dependencies before the review conclusion.

A review conclusion needs a reliable current baseline.

Open this interactive lesson →

LESSON 4

Compare options deliberately

Avoid introducing a new hazard while reducing another.

Process operators monitoring equipment from a UK industrial control room. Photorealistic illustration.
Photorealistic illustrative UK workplace scene. Review checks: Setting: the process operator, a fictional fuel terminal, proposes a temporary transfer-line bypass while a leaking section is replaced. Act: Hold the affected transfer. Hold / review: Do not introduce fuel if integrity, support, protection, test results, operating limits or emergency arrangements are uncertain, or if another credited barrier is impaired.

Compare options deliberately

A proposed improvement may remove one difficulty and introduce another. Compare credible alternatives, including whether the hazardous step can be removed or reduced. Examine operability, compatibility and affected protective functions rather than choosing the option with the most reassuring label.

The review should explain its assumptions and the basis for selection. Cost and convenience are relevant to planning but cannot replace required risk reduction. An awareness learner contributes observations and questions; specialist design choices and risk-acceptance decisions remain with the authorised competent process.

How should the review compare safer options?

Compare the proposed change with doing the task another way or removing its hazard. Then test the effect on connected plant, safeguards, people and operating limits before authorising the preferred option.

A replacement transfer pump may fit the pipework yet have different flow, pressure, material, seal or control behaviour. The engineer compares the required duty, process and chemical compatibility, downstream capacity, tank-overfill protection, electrical or hazardous-area suitability and maintainability. Operations checks the real startup, shutdown and abnormal states; maintenance checks access, isolation and replacement parts. A claimed like-for-like change needs evidence of equivalence.

Record the options, the hazards removed and introduced, the reason for rejecting stronger controls, the engineering assumptions and who can approve each decision. Update affected drawings and instructions, brief the people whose work changes, and verify the installation and protected commissioning checks before release. An unexplained new limit, missing design information or unverified safety function holds the change.

Sources and references

Sources: HSE COMAH plant modification and change procedures; HSE COMAH control systems; HSENI Control of Major Accident Hazards Regulations.

Applied case

Fictional exercise: A shorter transfer route reduces handling but connects the receipt to another inventory.

Benefit

One reduced exposure can be real.

New connection

A benefit does not erase another introduced pathway.

Test your decision

What is needed?

  1. Accept it solely because the route is shorter.
  2. Reject every improvement because change creates questions.
  3. Review both the benefit and the new connected scenario before selection.
Compare the explanation

Review both the benefit and the new connected scenario before selection.

Compare the complete changed arrangement.

Open this interactive lesson →

LESSON 5

Control temporary arrangements

Identify expiry, restrictions and restoration.

2D teaching diagram: Change the evidence before restarting
Existing SHAREhub 2D teaching schematic. Use alongside the explanation and fictional case in this lesson.

Control temporary arrangements

Temporary changes need defined conditions, authority, duration or review trigger and a restoration plan appropriate to the change. Without those arrangements a temporary workaround can quietly become the normal configuration.

Make its status visible to shifts, maintenance and anyone relying on the original arrangement. Expiry is not proof that conditions are safe or that restoration occurred. The responsible process must decide what happens before the temporary basis ends. Avoid inventing a universal permitted duration; the course supplies no such engineering or legal limit.

How are temporary changes prevented from becoming permanent by drift?

Give each temporary change a competent basis, owner, operating limit, expiry or trigger, monitoring and a plan for permanent correction or removal.

Track temporary pipes, overrides, software settings, repairs and staffing cover in a visible register. Reassess the hazard if circumstances or duration changes; an extension is a new decision, not an automatic date edit. Escalate combined temporary impairments that share a scenario. HSE COMAH plant modification and change procedures and HSE HSG254 Developing process safety indicators.

Make expiry an owned decision

Record maximum authorised duration and earlier withdrawal triggers, shift handover, cumulative impairments and the person who must stop the arrangement. An event-bounded duration needs a competent documented justification and a clear withdrawal condition. Expiry or failed conditions require withdrawal/hold; any extension needs fresh assessment and approval.

Applied case

Fictional exercise: A temporary bypass note has no responsible owner, review trigger or restoration condition.

Temporary

Time-limited does not mean low risk.

Restoration

The original arrangement must be demonstrably restored or formally reviewed.

Test your decision

What is missing?

  1. A course-selected universal expiry period.
  2. A controlled temporary basis with ownership, restrictions and restoration or review arrangements.
  3. Only a more prominent word “temporary”.
Compare the explanation

A controlled temporary basis with ownership, restrictions and restoration or review arrangements.

Temporary status requires practical controls, not a label.

Open this interactive lesson →

LESSON 6

Keep urgency within control

Distinguish expedited review from bypassed review.

2D teaching diagram: Pipeline receipt is a two-ended operation
Existing SHAREhub 2D teaching schematic. Use alongside the explanation and fictional case in this lesson.

Keep urgency within control

Urgent work may require an established expedited change route. That route still needs an appropriate competent decision, necessary controls and traceable communication. The emergency label cannot substitute for understanding the changed hazard.

Record the basis and remaining follow-up required by the arrangement. If the case provides no authorised emergency route, do not invent one. Immediate protective response and permanent plant modification are different decisions; a response that makes people safe is not blanket approval for an improvised operating configuration.

Can an emergency justify bypassing MOC?

Urgency can justify a shortened, proportionate review, but not absence of hazard assessment, competent authorisation, communication and later verification.

First make the plant safe. Define the immediate threat, minimum safe intervention, affected barriers and temporary limits. Record who authorised it and when the full review, documentation and restoration will occur. If safety cannot be demonstrated, hold operation rather than treat a production emergency as a safety exception. HSE COMAH plant modification and change procedures.

Applied case

Fictional exercise: A breakdown is called an emergency; no authorised expedited change arrangement is identified.

Response

Protective action addresses the immediate event.

Change

A changed operating configuration needs its authorised basis.

Test your decision

What is sound?

  1. Use the defined response and seek the appropriate authorised change decision.
  2. Treat urgency as approval for any modification.
  3. Continue an improvised arrangement until the next audit.
Compare the explanation

Use the defined response and seek the appropriate authorised change decision.

Urgency changes the response context, not the need for a justified decision.

Open this interactive lesson →

LESSON 7

Review organisational dependencies

Recognise competence and workload effects.

Process operators monitoring equipment from a UK industrial control room. Photorealistic illustration.
Photorealistic illustrative UK workplace scene. Review checks: Avoid / redesign: Engineering assesses removing the transfer step or redesigning the process so the hazardous operation is unnecessary. Control the task: Competent designers specify required containment, relief or protective control changes and maintainable isolation/access for the actual changed duty. Verify before release: Verify that the harm route has been removed rather than transferred.

Review organisational dependencies

Changing roles, staffing, contractor support or supervision can alter process control even when equipment stays the same. A task may depend on a competent person being available, an independent check or timely response to an abnormal condition.

Examine what work transfers, who can perform it and what happens when demands coincide. Avoid assuming a headcount alone proves adequacy or inadequacy. The review needs task and workload evidence, authority boundaries and transition arrangements. A revised organisation chart does not demonstrate that critical tasks remain achievable.

Why must organisational and staffing changes enter MOC?

A new structure can remove experience, increase workload or break ownership of a safety-critical task without altering hardware.

Map alarm response, permit authority, inspection, technical challenge, emergency command and out-of-hours cover before and after the change. Consult those doing the work, phase changes where possible, assess the transition itself and monitor whether the new arrangement works. HSE’s organisational-change guidance treats these as major-accident controls. HSE organisational change and major accident hazards and HSE CHIS7 Organisational change and major accident hazards.

Applied case

Fictional exercise: Two roles are combined; the review contains no analysis of simultaneous abnormal demands.

Unchanged plant

The equipment can stay identical while its human dependencies change.

Evidence

Task demands matter more than a headcount alone.

Test your decision

What should be examined?

  1. Only the new job title.
  2. A universal staffing ratio selected by the learner.
  3. The critical tasks, competence and workload under the changed arrangement.
Compare the explanation

The critical tasks, competence and workload under the changed arrangement.

Organisational changes can affect protective tasks and response.

Open this interactive lesson →

LESSON 8

Separate proposal from approval

Check the scope and conditions of an authorisation.

Process operators monitoring equipment from a UK industrial control room. Photorealistic illustration.
Photorealistic illustrative UK workplace scene. Review checks: Change at source: Engineering assesses removing the transfer step or redesigning the process so the hazardous operation is unnecessary. Make it observable: Verify that the harm route has been removed rather than transferred. Keep useful evidence: Retain screen, hazard study, technical approvals, as-built check, pressure/leak and function tests, procedure, competence, temporary expiry and final removal record.

Separate proposal from approval

A proposal, purchase order and approved change are different records. Approval should identify the reviewed scope, authorised role, conditions and outstanding hold points. An approval for one configuration does not automatically cover later additions.

Read conditions rather than looking only for a signature. Work may be authorised for installation while operation remains restricted until verification. If a document does not establish the relevant permission, state the gap. An awareness learner should not infer an operating release from spending approval or project completion pressure.

Who can authorise a change?

Define technical, operational and management authority before work starts. Approval should follow a completed risk review and explicit hold points, not a signature on an empty form.

Engineering checks design integrity and standards; operations checks plant state and usability; maintenance checks installation and testability; safety and emergency leads challenge consequences. The responsible manager owns resources, timing and release. A person cannot approve beyond their competence or waive unresolved high-consequence actions merely to meet a schedule. HSE COMAH plant modification and change procedures and HSE organisational change and major accident hazards.

Record the legal gate before installation

At proposal/design, the change owner records applicability, notifications, advance submissions and any statutory hold before construction or modification. In GB, MAPP and safety-report reviews have five-year backstops and earlier triggers. Significant modifications require review before modification and necessary revised report parts must reach the competent authority in advance. A new-establishment route has its own pre-construction/pre-operation or modification submission and conclusions gate. This is not regulator approval for every routine MOC. At handback confirm as-built conformity and close-out evidence. HSE L111: COMAH advance review/submission gates NI applicability and timing must be determined against its separate current COMAH instrument.

Applied case

Fictional exercise: A purchase order is approved; the change review still has an unresolved pre-start condition.

Purchase

Commercial approval enables procurement.

Operation

The operating release depends on its own conditions.

Test your decision

What is justified?

  1. The equipment must be faulty.
  2. Procurement approval does not establish permission to operate.
  3. Payment authorises every later step.
Compare the explanation

Procurement approval does not establish permission to operate.

Authorisations have a defined purpose and scope.

Open this interactive lesson →

LESSON 9

Verify what was actually installed

Compare the implemented arrangement with the approved scope.

Process operators monitoring equipment from a UK industrial control room. Photorealistic illustration.
Photorealistic illustrative UK workplace scene. Review checks: Setting: the process operator, a fictional fuel terminal, proposes a temporary transfer-line bypass while a leaking section is replaced. Act: Hold the affected transfer. Hold / review: Do not introduce fuel if integrity, support, protection, test results, operating limits or emergency arrangements are uncertain, or if another credited barrier is impaired.

Verify what was actually installed

Implementation can differ from the reviewed design through substitutions, field routing or undocumented adjustments. Verify the actual arrangement against the approved scope and record relevant deviations through the change process.

A completed work order establishes what it states, not every functional requirement. Tests need an appropriate procedure, competence and configuration. Awareness learning does not provide commissioning instructions. Its useful question is whether the specified evidence exists and concerns the actual installed arrangement, with unresolved items retained for the responsible decision.

How is installation controlled?

Implement only the approved design and work method. Coordinate isolation, permits, contractors, adjacent operations and design deviations as the work unfolds.

Use clear equipment identity, drawings, materials and quality checks. Stop and return to hazard review if a part, route or method differs from the approved change. Temporary devices and bypasses need visible status and expiry. An installation record should show what was actually built, not just what was planned. HSE COMAH plant modification and change procedures and HSE COMAH operating procedures.

Applied case

Fictional exercise: The installed component differs from the reviewed specification; no assessment of the substitution is supplied.

Installed

Physical work may be complete.

Verified

The approved requirements and deviations still need evidence.

Test your decision

What is needed?

  1. Review the deviation and establish the required verification before claiming conformity.
  2. Accept it because installation is complete.
  3. Assume the different component certainly fails.
Compare the explanation

Review the deviation and establish the required verification before claiming conformity.

Completion does not demonstrate conformity to the reviewed arrangement.

Open this interactive lesson →

LESSON 10

Respect pre-start hold points

Integrate equipment, information and people readiness.

2D teaching diagram: Change the evidence before restarting
Existing SHAREhub 2D teaching schematic. Use alongside the explanation and fictional case in this lesson.

Respect pre-start hold points

Pre-start review asks whether the agreed conditions for operation are met. Relevant items can include verification results, controlled instructions, competence, maintenance information and emergency implications. The exact set depends on the change.

A ticked checklist is meaningful only when its entries are supported. Separate completed installation from unresolved operating conditions. If a required item is open, use the defined hold point and authorised decision process. Do not treat a successful isolated test as proof that instructions, dependencies and people are all ready.

What must be checked before hazardous start-up?

A pre-start review confirms the installed change, safety functions, procedures, competence and emergency arrangements match the approved basis before hazardous material or energy is introduced.

Check punch-list items by consequence, pressure or leak tests as applicable, trip and alarm functions, valve line-up, control-system configuration, isolations removed under control, updated drawings and operator training. A test result must name the function and acceptance criteria. Do not transfer a temporary work permit into permanent operating approval. HSE COMAH plant modification and change procedures, HSE COMAH control systems and HSE COMAH operating procedures.

Applied case

Fictional exercise: Equipment testing is complete, but operators have not received the changed shutdown instruction.

Test

A test covers specified functions and conditions.

Readiness

Other required operating conditions still matter.

Test your decision

What remains?

  1. Nothing, because the equipment passed one test.
  2. A reason to delete the instruction requirement.
  3. The relevant information and competence readiness before the operating release.
Compare the explanation

The relevant information and competence readiness before the operating release.

Readiness connects plant, information and people.

Open this interactive lesson →

LESSON 11

Make the change survive handover

Keep controlled information aligned with actual work.

2D teaching diagram: Pipeline receipt is a two-ended operation
Existing SHAREhub 2D teaching schematic. Use alongside the explanation and fictional case in this lesson.

Make the change survive handover

A change affects more than the project folder. Drawings, operating instructions, maintenance tasks, training and relevant emergency information may need revision. Identify each affected owner rather than assuming one document update reaches every user.

Control superseded information and communicate what changed, why it matters and which conditions apply. Confirmation should test understanding of the role-relevant difference, not merely record that an email was sent. Preserve the rationale so future changes do not unknowingly remove a safeguard introduced for a past event.

How do procedures and training follow a change?

Update the controlled method, limits, abnormal response and role authorisation before people use the modified plant.

The operator should see the actual changed valve, tag, alarm or sequence in the procedure. Train by demonstration, not only circulation of a document. Remove superseded instructions and brief contractors and emergency responders where their tasks change. Keep the change record linked to these proof points. HSE COMAH operating procedures and HSE COMAH plant modification and change procedures.

Applied case

Fictional exercise: The project drawing is updated, but the maintenance task still names the old isolation arrangement.

Current use

People need the information matching the actual plant.

History

The decision rationale should remain traceable.

Test your decision

What is the issue?

  1. All historic records should be erased.
  2. The change has not been carried consistently into affected controlled information.
  3. The project drawing automatically updates every task.
Compare the explanation

The change has not been carried consistently into affected controlled information.

Affected work arrangements need their own controlled updates.

Open this interactive lesson →

LESSON 12

Close with evidence, not elapsed time

Integrate operation, monitoring and final records.

Process operators monitoring equipment from a UK industrial control room. Photorealistic illustration.
Photorealistic illustrative UK workplace scene. Review checks: Avoid / redesign: Engineering assesses removing the transfer step or redesigning the process so the hazardous operation is unnecessary. Control the task: Competent designers specify required containment, relief or protective control changes and maintainable isolation/access for the actual changed duty. Verify before release: Verify that the harm route has been removed rather than transferred.

Close with evidence, not elapsed time

Close-out should show that agreed actions, records and relevant reviews are complete. Some changes require defined initial monitoring or later effectiveness checks. Do not infer completion because the project budget closes or a temporary note has aged.

For the fictional exercise, state what is confirmed, what remains open and who owns its resolution. Preserve restrictions and temporary conditions until their proper decision. A well-organised pack is not itself a start permission; its value is the connection between the reviewed change, actual configuration and evidenced operating basis.

When is the change truly closed?

Close only when design intent is demonstrated, affected documents and training are updated, actions are verified and the operating owner accepts the installed state.

Record the as-built condition, residual limits, removed temporary devices, test evidence, revised procedures, maintenance tasks, inspection plan, emergency assumptions and any required safety-report revision. Assign a post-start review for a change whose performance needs observation. A closed form with missing field evidence is not close-out. HSE COMAH plant modification and change procedures and HSE HSG254 Developing process safety indicators.

Applied case

Fictional exercise: A modified route is installed and tested; an agreed post-start review and document update remain open.

Completion

Each agreed item needs its own evidence.

Closure

The responsible process decides closure with remaining conditions explicit.

Test your decision

Which status is accurate?

  1. Installation and stated tests complete; the remaining review and update are still open.
  2. All change obligations are complete because invoices are paid.
  3. The test proves no future review is useful.
Compare the explanation

Installation and stated tests complete; the remaining review and update are still open.

Close-out preserves separate evidence and action statuses.