CDM essentials for clients and small projects

Approximately 49–76 minutes

Workplace awareness and prevention. Specialist competence, statutory examinations and work authorisation require separate evidence. Check the relevant UK nation and actual workplace arrangements. Completion does not establish practical competence, authorise hazardous work or award an external qualification.

Read the complete core teaching here. Use the interactive course for required activities, saved assessment and conditional completion.

Recognise the project

Recognise the project

Recognise a construction project

CDM essentials for clients and small projects — explanatory workplace illustration
Professional teaching illustration. Read the written scenario for the facts; the image is not evidence of a real workplace.

Construction duties can apply to small refurbishment, installation and maintenance work as well as major building sites. Identify the client, designers and contractors and establish which national rules apply. A short duration does not remove the need for suitable arrangements.

Which CDM law applies in Great Britain and Northern Ireland?

CDM 2015 is GB law; CDM (Northern Ireland) 2016 is the separate NI instrument. Similar duties do not make either instrument UK-wide.

Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE CDM 2015 legal summary · HSENI CDM 2016 overview .

Both regimes cover all in-scope construction projects and require written principal appointments where more than one contractor is involved or reasonably foreseeable. Both require a construction phase plan for every project and a health and safety file for a multi-contractor project. Domestic-client duty transfer is set out in each regime. The notification test is more than 30 working days with more than 20 workers simultaneously at any point, or more than 500 person-days. Use GB F10 and NI NI10 respectively. A commercial client has the notification duty; on a domestic project regulation 7 passes that duty to the sole contractor, principal contractor or a principal designer with a written agreement to take client duties. Check each instrument for the project; NI schedules and numbering differ.

Sources for this explanation: Construction (Design and Management) Regulations 2015 ; Construction (Design and Management) Regulations (Northern Ireland) 2016 .

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

What are the Construction Design and Management Regulations?

Recognise the project

Recognise a construction project

UK building site with a segregated walkway and workers reviewing the site
Existing SHAREhub photographic illustration. The fictional case supplies the task and decision evidence.

Construction duties can apply to small refurbishment, installation and maintenance work as well as major building sites. Identify the client, designers and contractors and establish which national rules apply. A short duration does not remove the need for suitable arrangements.

What are the Construction Design and Management Regulations?

The Construction Design and Management Regulations are construction health and safety regulations that require projects to be planned, coordinated and controlled from concept to completion. CDM exists because construction risks are often created long before a worker steps onto site. A design can make roof access safer or dangerous. A client can allow enough time and budget or force rushed work. A contractor can plan a safe sequence or improvise around missing information. The regulations create named dutyholders so responsibility does not disappear between organisations.

They require cooperation, coordination and communication between the people who commission, design and build. A strong CDM project feels organised: the right people are appointed early, hazards are known, the construction phase plan is specific, welfare is ready, workers are briefed, contractors are coordinated and the health and safety file is useful at handover.

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

What is a construction phase plan?

Recognise the project

Recognise a construction project

Contractor induction and coordination meeting at a UK worksite
Existing SHAREhub photographic illustration. The fictional case supplies the task and decision evidence.

Construction duties can apply to small refurbishment, installation and maintenance work as well as major building sites. Identify the client, designers and contractors and establish which national rules apply. A short duration does not remove the need for suitable arrangements.

What is a construction phase plan?

A construction phase plan is the written project plan for managing health, safety and welfare during construction work. The CPP sits between pre-construction planning and work as done on site. It should take the project information, design decisions, known hazards, site constraints and programme, then explain how the construction phase will be organised and controlled. Its value is practical: it gives the project team a common operating framework before people, plant and materials arrive on site. A good CPP is specific to the project. It identifies who is in charge, how contractors will cooperate, what site rules apply, what welfare is provided, how emergencies will be managed, which high-risk activities need special arrangements and how the principal contractor or contractor will monitor the work.

The plan should be detailed enough to manage foreseeable risks but simple enough for the project team to use. A long generic document can fail because people cannot find the controls that matter. A short plan can be suitable for simple work if it genuinely covers the risks and arrangements.

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

Appoint and inform

Appoint and inform

Identify dutyholders and appointments

Engineered temporary props and formwork on a UK site
Existing SHAREhub photographic illustration. The fictional case supplies the task and decision evidence.

For Great Britain projects involving more than one contractor, written principal designer and principal contractor appointments are required. Give relevant pre-construction information and allow suitable time and resources. Check capability for the actual work rather than relying on generic certificates.

When and how must principal dutyholders be appointed?

For a known or reasonably foreseeable multi-contractor project, a commercial client appoints a designer in control and a contractor in writing as soon as practicable, before construction begins.

Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE principal designers · HSE planning for construction work .

The principal designer should start early enough to influence concept and design risk. The principal contractor must be appointed early enough to help plan the construction phase and prepare the plan. If a commercial client omits either appointment, the client must fulfil that principal role duty; it remains responsible for the project arrangements. For a domestic client who does not appoint, regulation 7 assigns principal-designer duties to the designer in control and principal-contractor duties to the contractor in control; client duties also transfer under the domestic route. A later second trade triggers a fresh assessment immediately, not only at the next contract renewal.

Sources for this explanation: HSE commercial clients ; HSE domestic clients ; HSENI CDM 2016 overview .

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

When must a construction project be notified?

Appoint and inform

Identify dutyholders and appointments

CDM essentials for clients and small projects — explanatory workplace illustration
Professional teaching illustration. Read the written scenario for the facts; the image is not evidence of a real workplace.

For Great Britain projects involving more than one contractor, written principal designer and principal contractor appointments are required. Give relevant pre-construction information and allow suitable time and resources. Check capability for the actual work rather than relying on generic certificates.

When must a construction project be notified?

CDM applies before notification is considered. Notify only if a statutory threshold is forecast to be met, using the correct GB or NI regulator route.

Both HSE and HSENI describe a project as notifiable when construction work is scheduled to last longer than 30 working days and have more than 20 people on site at any time , or when it exceeds 500 person-days . The tests are alternatives. Keep a dated programme and labour forecast, review them as the project changes and notify in time when the test is met. These thresholds do not decide whether a principal designer, principal contractor, construction phase plan, welfare or cooperation are needed.

In Great Britain the client normally uses HSE’s F10 route, with special arrangements for domestic projects and some regulator-specific sites. In Northern Ireland the client notifies HSENI under CDM (NI) 2016 using its NI route, commonly NI10; the GB F10 is not the NI notification. Verify the receiving authority and form on the current regulator page, especially for specialist sites. The HSENI NI10 PDF linked below is marked non-accessible; request an accessible route from HSENI if needed.

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

How does the CPP link to building safety and the health and safety file?

Appoint and inform

Identify dutyholders and appointments

Contractor induction and coordination meeting at a UK worksite
Existing SHAREhub photographic illustration. The fictional case supplies the task and decision evidence.

For Great Britain projects involving more than one contractor, written principal designer and principal contractor appointments are required. Give relevant pre-construction information and allow suitable time and resources. Check capability for the actual work rather than relying on generic certificates.

How does the CPP link to building safety and the health and safety file?

The CPP should control construction-phase risk while also helping capture information needed for future maintenance, use and alteration. The CPP is primarily about health and safety during construction, but it should connect to the information flow for the completed asset. Design changes, temporary works decisions, concealed services, fire-stopping, structural changes, access arrangements and residual hazards may need to be captured for the health and safety file or wider building information requirements. For applicable higher-risk building work in England, the CPP should not be treated as the only compliance document.

It should sit alongside building regulation, fire safety, quality assurance and golden-thread information arrangements so construction decisions are controlled and recorded properly. The construction phase plan is required for every project. GB L153 distinguishes the health and safety file, required for projects involving more than one contractor, from the plan. NI has its separate CDM 2016 instrument and local file/plan duties. For applicable higher-risk building work in England, BSR golden-thread guidance describes client, principal designer and principal contractor information arrangements. Do not apply that England regime as a UK-wide rule.

Capture relevant as-built information through controlled updates and handover.

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

Verify the start conditions

Verify the start conditions

Check pre-start planning and information

Workers reviewing a permit beside safely isolated industrial equipment
Existing SHAREhub photographic illustration. The fictional case supplies the task and decision evidence.

A construction phase plan is needed before the construction phase starts; notification thresholds are a separate question. Confirm welfare, coordination and public protection. Use the Northern Ireland CDM route where applicable and obtain competent advice on uncertain project boundaries.

How should the client test an appointment?

Check the role definition, actual control, project-specific skills, knowledge, experience and organisational capability before recording a clear written appointment. Ask who will make design and site decisions, what time and resources they have, and how they will coordinate the other parties. The check should match risk and complexity. Relevant experience, team availability, supervision, previous performance and design or construction expertise may help. Membership, insurance, third-party schemes and training records can support a proportionate assessment but none is a universal substitute for capability or a fixed CDM legal checklist.

Sources for this explanation: HSE CDM dutyholder summary; HSE CDM frequently asked questions.

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

Which legal duties apply to CDM?

Verify the start conditions

Check pre-start planning and information

UK building site with a segregated walkway and workers reviewing the site
Existing SHAREhub photographic illustration. The fictional case supplies the task and decision evidence.

A construction phase plan is needed before the construction phase starts; notification thresholds are a separate question. Confirm welfare, coordination and public protection. Use the Northern Ireland CDM route where applicable and obtain competent advice on uncertain project boundaries.

Which legal duties apply to CDM?

Use CDM 2015 for Great Britain and CDM (Northern Ireland) 2016 for Northern Ireland; check hazard-specific law in the same jurisdiction.

Clients must make suitable arrangements and provide relevant pre-construction information. Where more than one contractor is involved or likely, the principal designer and principal contractor roles need appointment; the construction phase plan is not limited to notifiable jobs. Designers eliminate or reduce foreseeable risk and pass on significant residual information. Contractors plan, manage and monitor their work and cooperate with the project team. The precise legal route and any domestic-client transfer depend on GB or NI law and project facts.

England Building Regulations dutyholder roles are a separate building-control regime. A project may need both sets of decisions, but do not treat England building-control law as GB-wide or NI CDM law. Work at height, asbestos, fire, lifting and welfare obligations also require their own location-specific legal check.

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.

Open the interactive lesson

What evidence shows a CPP is working?

Verify the start conditions

Check pre-start planning and information

CDM essentials for clients and small projects — explanatory workplace illustration
Professional teaching illustration. Read the written scenario for the facts; the image is not evidence of a real workplace.

A construction phase plan is needed before the construction phase starts; notification thresholds are a separate question. Confirm welfare, coordination and public protection. Use the Northern Ireland CDM route where applicable and obtain competent advice on uncertain project boundaries.

What evidence shows a CPP is working?

Evidence should show that the CPP is understood, implemented, checked and updated during the project. A CPP that sits in a file is not evidence of control. Useful evidence includes inductions, site-rule briefings, supervisor inspections, contractor coordination meetings, permit records, welfare checks, emergency drills, action close-out, design change briefings, worker consultation and revision history. Field evidence matters. If the CPP says pedestrians are segregated but the site layout shows workers crossing plant routes, the plan is not working. If it says welfare is available but washing facilities are missing, the plan is not working.

If it says high-risk work is controlled by permits but permits are copied or missing, the plan is not working.

Fictional workplace decision

Fictional case — A commercial client commissions a small refurbishment with two contractors. The programme appears below notification thresholds, and the client assumes no CDM appointments or construction planning are needed.

Compare the reasoning

Check the project's actual CDM duties independently of whether notification thresholds are met. The commercial client should establish the applicable jurisdiction, required appointments, planning and welfare arrangements for this multi-contractor refurbishment. A small or non-notifiable project still needs suitable coordination; the programme label does not supply the missing evidence.