Risk-based inspection and audit programme

BOUK-PLN-MON-01 · v2.2 · Completed fictional example · DOCX

Schedule assurance by risk, change and performance; distinguish statutory inspections.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

Completed example for January to December 2027 | BOUK-PLN-MON-01 | Version 2.2 | 23 October 2026

FICTIONAL WORKED PLAN — BuildOut is the SHAREhub example business. The four named sites, work phases, risk inputs and programme below are invented. Checks and audits are planned, not completed; no real findings, signatures or approvals are claimed.

We will assure every active work package through supervisor checks, site-manager challenge and a separate risk-based audit programme. The 12-month plan connects the site portfolio, risk inputs R01–R26, activity checks C01–C26 and formal audits A01–A12, including A06B. A failed critical control stops the affected work regardless of an overall score or calendar date.

Plan controlCompleted example arrangement
ScopeCommercial refurbishment, retail fit out, light industrial construction and residential development. About 50 direct employees and 50–150 subcontract workers across changing projects.
Plan owner and sponsorCompetent H&S adviser maintains the programme. Contracts / Operations Manager owns delivery capacity. Managing Director / board sponsors resources and escalation.
Operating period1 January–31 December 2027. Baseline planning snapshot: 1 January 2027. Monthly review and immediate replan after material change.
Delivery modelTrade Supervisor checks every live task. Site Manager makes weekly site checks and monthly risk-focused observations. Competent reviewers conduct the formal audits.
Linked management systemExisting example policy and document register for Build Out UK Limited. Covers all 35 policy areas and their 271 listed management documents through the domain-to-audit mapping.
Adoption and approvalPrepared example only. Local scope, people, resources and technical arrangements require genuine review and authorisation before use. No signature is prefilled.

How to use the plan

Start with the site portfolio, then use the risk/check catalogue to select every applicable control check. Follow the monthly additional focus and audit programme without dropping the standing checks. Use the final coverage register to identify the policy, procedure, assessment, permit or record to examine. Keep actual results and approvals in separate blank operational records.

Current example sites and work phases

These are the four active sites in this worked planning scenario, not a list of BuildOut’s actual live projects. ALL in the catalogue means S01 Jan–Sep, S02 Jan–Jun and S03/S04 Jan–Dec. HQ denotes company support processes, with no invented office address. Dates are planned phases and must move when the construction programme changes.

Site and periodWork and exposure profileAccountability
S01 Eastfield commercial refurbishment
Jan–Sep
Jan–Feb surveys and strip out; Feb–Apr structural alterations; Apr–Jul services; Aug–Sep finishes and handover. Occupied neighbour interface throughout.
Principal register inputs: R01–R05, R07–R15, R17–R20, R23–R26
Site Manager S01; Project Manager S01
S02 Harbour retail fit out
Jan–Jun
Jan–Apr evening fit out beside trading areas; May commissioning; Jun handover. Client evacuation and out-of-hours interfaces are critical.
Principal register inputs: R01–R04, R08–R20, R23–R26
Site Manager S02; Project Manager S02
S03 Foundry light industrial build
Jan–Dec
Jan–Apr groundworks; Apr–Jul frame; Jun–Aug roof; Aug–Oct services; Oct–Dec fit out. Lifting and temporary stability require stage checks.
Principal register inputs: R01–R06, R09–R15, R17–R21, R23–R26
Site Manager S03; Project Manager S03
S04 Meadow residential development
Jan–Dec
Jan–Jun groundworks; Apr–Sep frames and roofs; Jul–Dec fit out. Concurrent trades, deliveries and changing public boundaries.
Principal register inputs: R01–R06, R09–R15, R17–R21, R23–R26
Site Manager S04; Project Manager S04

Site changes and demobilisation

Each Site Manager checks the next eight weeks of work every Friday with Trade Supervisors and the Project Manager. Add new activities, risks and specialist interfaces before they enter the work programme. The H&S adviser updates this plan within two working days of an accepted change; affected work remains held while essential controls are unresolved. These are company-set example planning times, not statutory deadlines.

S02 closes in June and S01 in September. Their audits and critical action verification occur before handover. Archive the final register, survey restrictions, design information and client transfer evidence. November can review those records but cannot retrospectively observe controls at a closed site. Any follow-on or reopened site needs a fresh mobilisation review.

Risk basis roles and minimum check frequency

The risk inputs are an original populated example, using the activity, hazard, controls, owner and evidence logic of the existing construction register. P1–P3 set assurance intensity; they are planning priorities, not numerical risk acceptance bands or permission to work. Scores and residual-risk decisions belong in the site’s competent task assessment.

PrioritySupervisor responsibilitySite Manager responsibility
P1 serious acute or latent harmCheck every active workface before work and after change; verify each critical stage before release. Observe controls during the task and record the result each shift.Weekly field check at every active site and at least one direct monthly observation of each active P1 work package; increase sampling after failure or change.
P2 significant recurring exposureCheck before the task and when conditions change. Complete one structured recorded sample per active trade each week, including actual duration and exposure controls.Monthly sample of each active P2 activity, with different trades or shifts where practicable; check required specialist evidence.
P3 lower-consequence routine workCheck on first use and after change. Review worker-reported defects promptly and record the applicable local checks.Monthly representative office/support sample; individual adjustment or defect actions remain separately tracked.

The Site Manager’s weekly inspection is a separate challenge of current work, not a substitute for supervisors’ task checks. The monthly focus adds depth and changes the observation time or workface. Specialist examinations, statutory inspections, exposure monitoring and health surveillance retain their own competent methods and required intervals. This assurance calendar does not replace them.

Enduring risks to the business

Register inputAssurance response
E01 weak ownership or insufficient resourcesContracts Manager reviews workload and cover monthly; A01 tests readiness and A12 resources the next year. Unstaffed critical checks prevent the affected release.
E02 unsuitable contractors or competenceC26 and A08 trace procurement through actual delivery, subcontracting and supervision. A11 challenges independence and consistency.
E03 stale design or task informationC26 and A01/A09 test version control and changed work. A new or changed task is mapped before work starts.
E04 misleading assurance or repeated failureA11 tests coverage and evidence quality; A12 reviews recurrence and action effectiveness. Missing evidence is reported, never converted into a pass.

Risk register inputs and activity checks 1 to 7

Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.

Risk and priorityActivity check and evidenceWhere and whenAudit links
R01 P2
Site establishment and welfare
C01
Inspect access, welfare, housekeeping and workface layout; compare the current construction phase plan with the shift.ALLA01 A04 A10
R02 P1
Vehicle and public interfaces
C02
Observe a real delivery and separated pedestrian route; verify barriers, marshal positions and safe waiting arrangements.ALLA03 A04 A10
R03 P1
Falls and dropped objects
C03
Verify edge protection, openings, safe access and falling-object controls at each live workface; record scaffold or access reference.S01 Feb–Sep; S02 Jan–Apr; S03 Apr–Dec; S04 Apr–DecA02 A06 A10
R04 P1
Lifting operations
C04
Match lift plan, people, equipment evidence, ground support and exclusion to the actual lift; witness critical-stage release.S01 Feb–Apr; S02 Jan–Apr; S03 Apr–Aug; S04 Feb–SepA03 A06 A11
R05 P1
Temporary works and stability
C05
Trace design, check category, loading restrictions, installation inspection and permit to load or dismantle to the installed works.S01 Feb–Apr; S03 Jan–Aug; S04 Jan–SepA02 A03 A06
R06 P1
Excavation collapse and services
C06
Match service information and detection to excavation; verify support, access, exclusion and competent inspection evidence before entry.S03 Jan–Apr; S04 Jan–JunA03 A06 A10
R07 P1
Demolition and structural alteration
C07
Verify survey and design scope, sequence, isolation, stability and exclusion before each structural stage; stop unassessed changes.S01 Jan–AprA02 A09 A11

Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.

Risk register inputs and activity checks 8 to 14

Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.

Risk and priorityActivity check and evidenceWhere and whenAudit links
R08 P1
Asbestos disturbance
C08
Check exact task footprint against survey scope and exclusions; no intrusive release for unknown material or missing specialist handback.S01 Jan–Jul; S02 Jan–AprA02 A04 A09
R09 P1
Dust and hazardous substances
C09
Observe cutting, mixing or application; verify source control, extraction or wet method, suitable RPE and task assessment.ALL while exposure tasks runA05 A08 A11
R10 P2
Noise exposure
C10
Compare actual tools, duration and nearby people with exposure assessment; check quieter method, segregation and protection.ALL while noisy work runsA05 A08 A11
R11 P2
Vibration exposure
C11
Verify tool choice, maintenance, actual trigger-time recording and assessment; investigate changed duration or symptoms confidentially.ALL while vibrating tools runA05 A08 A11
R12 P2
Manual handling and ergonomics
C12
Observe delivery-to-use handling; verify mechanical aids, load and route design and team capability against the task.ALLA04 A05 A08
R13 P1
Plant and powered tools
C13
Observe guarding, isolation, condition and authorised use; match equipment inspection or maintenance evidence to asset ID.ALLA03 A06 A10
R14 P1
Electrical installation and isolation
C14
Verify supply protection, condition and authorised isolation with a competent person; inspect evidence of dead-working controls and handback.ALL; commissioning S01 Jul, S02 May, S03 Oct, S04 Oct–DecA04 A07 A10

Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.

Risk register inputs and activity checks 15 to 20

Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.

Risk and priorityActivity check and evidenceWhere and whenAudit links
R15 P1
Fire and hot work
C15
Check occupied routes, combustible control, permit precautions and the risk-assessed fire-watch arrangements; never use a universal watch duration.ALL; hot work only under authorised methodA04 A07 A10
R16 P1
Confined-space work
C16
Screen for confined spaces before each new package. If entry becomes necessary, require specialist assessment, isolation and practicable rescue.No entry planned. All sites screen every lookahead; entry hold remains until authorised.A01 A03 A10
R17 P1
Permits and hazardous-energy isolation
C17
Trace one live permit from task scope to physical isolation, interfaces, shift handover and cancellation; verify authorised roles.ALL where permits applyA04 A07 A10
R18 P2
Occupational health and fitness
C18
Check exposure-to-surveillance referral and fitness restrictions through authorised summaries; do not include diagnoses in shared logs.ALL and company supportA05 A08 A11
R19 P2
PPE and RPE suitability
C19
Confirm equipment selection, compatibility, condition and required face-fit evidence against the actual task; observe correct use.ALL where requiredA05 A08 A11
R20 P1
Emergency response and first aid
C20
Check current access, alarm, first-aid cover and task rescue capability; test arrangements safely after layout or staffing changes.ALL; exercises Mar and Oct at each active siteA04 A06 A10

Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.

Risk register inputs and activity checks 21 to 26

Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.

Risk and priorityActivity check and evidenceWhere and whenAudit links
R21 P1
Weather and work near water
C21
Check forecast, ground and structural conditions against task limits. Screen water interfaces; no water work planned without separate assessment.S03 S04 all year; S01 S02 where external work changesA03 A06 A10
R22 P3
Office DSE and lone working
C22
Check workstation changes, lone-work contact arrangements and safe access; verify adjustment actions with the worker.HQ all year; each active site officeA01 A08 A11
R23 P2
Driving and work travel
C23
Sample journey planning, fatigue arrangements, vehicle condition and driver authorisation; challenge deadlines causing unsafe travel.ALL and company supportA08 A10 A11
R24 P1
Gas and combustion equipment
C24
Screen use and installation; verify competent specialist, isolation, ventilation and commissioning evidence before acceptance.S02 May; S01 Jul; S03 Oct; S04 Oct–Dec; no unplanned useA04 A07 A10
R25 P1
Specialist and simultaneous work
C25
Compare adjacent trades and client operations with the coordination plan; confirm one interface owner, boundaries and change release.ALL; occupied interface S01 S02A02 A04 A07
R26 P1
Unassessed task or control change
C26
Match every work package to register risks, current RAMS, competent supervisor and worker briefing; hold unmapped or changed work.ALL and each new subcontract packageA01 A08 A11

Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.

Twelve month activity checklist schedule January to June

Standing programme in every active month: supervisors check all current tasks under C01–C26 as applicable; Site Managers complete the weekly inspection and monthly P1/P2 observations. The additional focus below deepens that work. It must not become the only task checked that month.

Month and active sitesAdditional risk based focusManager observation and evidenceFormal audit
Jan
S01 S02 S03 S04
C01 C02 C08 C26Verify every live package is mapped before mobilisation; S01/S02 survey gaps held; S03/S04 groundworks releases checked.A01
Feb
S01 S02 S03 S04
C03 C05 C07 C08 C25S01 structure and asbestos boundaries; S03/S04 ground conditions; observe changed occupied interfaces at S02.A02
Mar
S01 S02 S03 S04
C02 C06 C13 C20 C21Sample an excavation and busy delivery at each relevant site; safe emergency exercise at all four active sites.A03
Apr
S01 S02 S03 S04
C03 C04 C05 C15 C17Observe critical frame/lift stages at S03/S04 and evening occupied-fit-out permits/fire precautions at S02.A04
May
S01 S02 S03 S04
C09 C10 C11 C12 C18 C19Compare exposure controls with observed tools and duration; include subcontractors and sensitive health referrals without clinical detail.A05
Jun
S01 S02 S03 S04
C03 C04 C05 C20 C26S04 frame/rescue checks; S02 commissioning and all critical closeout actions checked before its June handover.A06 A06B

Monthly delivery record

By the fifth working day of the following month, each Site Manager reconciles the task register with recorded checks, including evening work, subcontractors and work after layout changes. Record missing checks as exceptions with an owner and response. Confirm all active P1 work packages received direct manager observation; report any safe-observation limitation and the alternative evidence agreed.

Twelve month activity checklist schedule July to December

Standing programme in every active month: supervisors check all current tasks under C01–C26 as applicable; Site Managers complete the weekly inspection and monthly P1/P2 observations. The additional focus below deepens that work. It must not become the only task checked that month.

Month and active sitesAdditional risk based focusManager observation and evidenceFormal audit
Jul
S01 S03 S04
C14 C15 C17 C24 C25S01 services handback and gas interface; S03 roof boundaries; S04 frame-to-fit-out interfaces.A07
Aug
S01 S03 S04
C09 C12 C18 C22 C23 C26Check new subcontract packages and competence, heat/fatigue and consultation; test one register change at each active site.A08
Sep
S01 S03 S04
C01 C08 C14 C17 C26S01 final restrictions and residual risks transferred before closure; verify S03/S04 phase changes and live work scope.A09
Oct
S03 S04
C02 C15 C20 C21 C24Both sites repeat winter, access and fire checks after layout changes; safe emergency exercise and specialist commissioning checks.A10
Nov
S03 S04 plus HQ
C01–C26 as applicableIndependent system audit tests all policy domains. Managers produce open-risk and missed-check lists without pre-filling results.A11
Dec
S03 S04 plus HQ
C20 C21 C23 C26Verify outstanding actions before shutdown/restart arrangements; confirm future phases, new risks and 2028 coverage.A12

Monthly delivery record

By the fifth working day of the following month, each Site Manager reconciles the task register with recorded checks, including evening work, subcontractors and work after layout changes. Record missing checks as exceptions with an owner and response. Confirm all active P1 work packages received direct manager observation; report any safe-observation limitation and the alternative evidence agreed.

Formal site and system audit programme January to May

Formal audits test how site-wide arrangements produce effective controls. They include records, interviews and work observation and are separate from routine inspections. Auditors must be competent and sufficiently independent of the work they assess; a peer review’s limitations are declared. Days below are example resource allocations and increase if coverage cannot be achieved.

Audit month and scopeRisk and system focusLead resource and minimum sample
A01 Jan
HQ plus mobilisation review at all sites
Governance, legal schedule, CDM appointments, design risk, register completeness and readiness. E01–E04; R01 R16 R22 R26.H&S adviser with Contracts Manager and Design Manager; 2 auditor-days
Four project baselines, one design-change trail per site, complete risk-to-task map. Escalate missing prerequisites before work.
A02 Feb
S01 full site audit
Strip out, asbestos boundaries, structural alteration, temporary works and occupied interface. R03 R05 R07 R08 R25.H&S adviser plus competent structural/asbestos input; 1.5 days
All live critical fronts and their release records; interview two supervisors and three workers; trace every open high-risk hold.
A03 Mar
S03 full site audit; S04 comparison
Groundworks, services, lifting set-up, plant, weather and emergency arrangements. R02 R04 R05 R06 R13 R16 R21.Peer Project Manager and competent H&S adviser; 1.5 days
Observe one excavation and delivery at each active sample; compare three permit/inspection records; test drawing-to-workface match.
A04 Apr
S02 full site and client interface audit
Occupied retail fit out, survey scope, fire, electrical work, permits and contractor control. R01 R02 R08 R12 R14 R15 R17 R20 R24 R25.Independent peer Site Manager with H&S adviser; 2 days
Cover an evening shift, client handover and one live controlled task. Test all applicable site-system domains in the coverage register.
A05 May
S01 and S04 field visits; all-site records
Dust, COSHH, noise, vibration, handling, RPE and occupational-health arrangements. R09 R10 R11 R12 R18 R19.Competent occupational hygienist/adviser and H&S adviser; 2 days
Observe at least one highest-exposure task per visited site; review assessment and monitoring representativeness at all four sites.

Formal site and system audit programme June to August

Formal audits test how site-wide arrangements produce effective controls. They include records, interviews and work observation and are separate from routine inspections. Auditors must be competent and sufficiently independent of the work they assess; a peer review’s limitations are declared. Days below are example resource allocations and increase if coverage cannot be achieved.

Audit month and scopeRisk and system focusLead resource and minimum sample
A06 Jun
S04 full site audit
Frames, lifting, temporary works, work at height and rescue. R03 R04 R05 R06 R13 R20 R21.Peer Project Manager and competent lifting/temporary-works reviewers; 1.5 days
All live critical-stage releases; one installed system back to design and inspection; interview different trades.
A06B Jun
S02 closeout before demobilisation
Outstanding actions, client handback, commissioning and residual risks. R08 R14 R15 R17 R20 R24 R25.H&S adviser independent of S02 delivery; 0.5 day
All critical actions and client restrictions. Preserve evidence for A11; do not defer closeout to the November review.
A07 Jul
S01 full site pre-handover audit
MEP isolation, testing, gas specialist interface, permits and occupied-building handback. R14 R15 R17 R24 R25.Peer Project Manager plus competent services reviewer; 1 day
One complete isolation-to-reinstatement trail and all safety-critical commissioning exceptions; test current site-wide controls.
A08 Aug
HQ with S03 and S04 site samples
Procurement, subcontractors, competence, consultation, health, fatigue, driving and change. E01 E02 E03; R09–R12 R18 R19 R22 R23 R26.H&S adviser with Procurement and People coordinators; 2 days
Two contractor packages per visited site, agency/apprentice briefing where present, one concern through to response and one changed work package.

Formal site and system audit programme September to December

Formal audits test how site-wide arrangements produce effective controls. They include records, interviews and work observation and are separate from routine inspections. Auditors must be competent and sufficiently independent of the work they assess; a peer review’s limitations are declared. Days below are example resource allocations and increase if coverage cannot be achieved.

Audit month and scopeRisk and system focusLead resource and minimum sample
A09 Sep
S01 closeout and project learning
Handover, residual hazards, design changes and verified actions. R07 R08 R26; E03 E04.Contracts Manager and H&S adviser outside S01 action ownership; 1 day
All critical actions, representative major actions and the final client information transfer. Preserve evidence for A11.
A10 Oct
S03 and S04 full site audits
Changed phases, winter readiness, fire, traffic, electrical/gas work, permits and emergencies. R01–R06 R13–R17 R20 R21 R23–R25.Cross-project H&S/engineering audit team; 3 auditor-days
Separate site reports; cover current work fronts, one delivery and one emergency communication test at each site; earlier-domain checks revisited.
A11 Nov
HQ and S03/S04; S01/S02 archived evidence
Independent management-system implementation audit across all 35 policy areas and their subordinate requirements. E01–E04; R01–R26.Independent competent auditor not owning the assessed controls; 4 auditor-days
Risk-led samples plus 100% domain coverage. Closed-site conclusions use retained records and state the absence of current field observation.
A12 Dec
HQ board review and S03/S04 follow-up
Compliance evaluation, audit gaps, action effectiveness, objectives and the next annual plan. E01–E04; all unresolved risks.Managing Director/board with H&S adviser; 1 day plus follow-up
All critical/overdue findings, incomplete domain coverage, worker concerns, exposure trends and justified resources for the next year.

Detailed audit plan for A03 groundworks and site controls

Objective: determine whether S03’s management arrangements keep excavation, service and plant controls effective during real work, then compare a targeted S04 sample. The peer Project Manager leads; the H&S adviser and competent excavation/services reviewer support technical judgements. The delivery manager cannot independently verify their own disputed finding.

Audit stagePlanned test and evidence
Before the visitObtain the current register, construction phase plan, task inventory, legal schedule, design/service information, permits, inspection records, competence evidence and prior actions. Confirm activity timings and a safe observation position.
09:00–09:30 openingConfirm scope, criteria, live operations, restrictions, worker participation and reporting route. Identify inaccessible areas and evidence not yet available.
09:30–11:30 field observationAt S03 observe one live excavation workface, one plant/pedestrian interface and one controlled service-crossing task if safely active. Compare actual boundaries, access and equipment to the method. Stop and escalate an ineffective critical control immediately.
11:30–12:30 evidence trailTrace three excavation/permit/inspection records across more than one day. Select at least one changed work package. Verify reference, scope, competent role and whether the recorded condition matches the workface.
13:00–14:00 people and systemInterview the Site Manager, two supervisors and three workers across trades. Test understanding, consultation, induction, subcontractor coordination, welfare and emergency access; attendance alone is insufficient.
14:00–15:00 follow-throughTrace all open critical findings and two purportedly closed major actions. Check the physical outcome and the effectiveness test, with remaining limitations. Check design/change control and current document versions.
15:00–16:00 conclusionsDistinguish observed fact, missing evidence and inference. Agree containment, owners, deadlines and verification criteria; the audited manager may dispute facts with evidence but cannot remove an unresolved finding.
Second site and reportingUse the remaining half-day for S04 comparison and report completion. Expand the scope or add time if significant differences or gaps appear. Issue a scoped report within five working days; critical findings are communicated immediately.

Sample sizes are minimum starting points. Add samples for contradictory evidence, high turnover or repeated failure. An unavailable critical activity is not marked passed: record the limitation and schedule an observation before or during its next safe occurrence. The report states what the sample does and does not establish.

Management system coverage register 1 to 9

Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.

Policy requirement areaRisk and check linksAudit referencesImplementation evidence to test
BOUK-HS-001
Health and safety management
E01 E04
C26
A01 A11 A12Policy intent, role authority, resources and arrangements traced into site decisions.
BOUK-POL-GOV
Leadership and document control
E01 E03 E04
C26
A01 A11 A12Controlled issue, legal change, objectives and board decisions reach current site instructions.
BOUK-POL-CDM
CDM project delivery
E01 E02 E03 R26
C01 C25 C26
A01 A04 A09 A11Appointments, construction phase plan and handover follow actual dutyholder scope.
BOUK-POL-DES
Design risk management
E03 R05 R07 R26
C05 C07 C26
A01 A02 A09 A11Design hazards, residual information and revisions match installed and altered work.
BOUK-POL-RISK
Risk assessment and RAMS
E03 R01–R26
C01–C26
A01 A08 A11All live tasks mapped; assessment and method changes briefed and controlled.
BOUK-POL-COMP
People and competence
E01 E02 R26
C26
A01 A08 A11Task competence, authorisation, supervision and absence cover evidenced at work.
BOUK-POL-CONS
Worker consultation
E04 R26
C26
A08 A11 A12Workers and subcontractors influence controls; a concern has a recorded response.
BOUK-POL-SUB
Contractors and procurement
E02 R25 R26
C25 C26
A04 A08 A11Procurement evidence and subcontracted scope match the actual method and interfaces.
BOUK-POL-WEL
Site establishment and welfare
R01
C01
A04 A10 A11Welfare, work environment and changing site access inspected against use.

Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.

Management system coverage register 10 to 18

Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.

Policy requirement areaRisk and check linksAudit referencesImplementation evidence to test
BOUK-POL-WAH
Work at height
R03
C03
A02 A06 A10 A11Edge/opening/access and falling-object controls verified at live workfaces.
BOUK-POL-LIFT
Lifting operations
R04
C04
A03 A06 A11Lift planning and competent roles traced to equipment, ground and exclusion.
BOUK-POL-PLANT
Plant and work equipment
R13
C13
A03 A06 A10 A11Equipment procurement, maintenance, inspection and safe isolation match assets.
BOUK-POL-ELEC
Electrical safety
R14
C14 C17
A04 A07 A10 A11Electrical competence, isolation and test evidence support safe reinstatement.
BOUK-POL-TW
Temporary works and stability
R05
C05
A02 A03 A06 A11Temporary-works design, check, inspection and release chain preserved.
BOUK-POL-EXC
Excavations and buried services
R06
C06
A03 A06 A11Service detection, support and competent inspection correspond to excavation.
BOUK-POL-DEM
Demolition and structural alteration
R07
C07
A02 A09 A11Structural survey, sequence, stability and exclusion reflected in stage releases.
BOUK-POL-ASB
Asbestos
R08
C08
A02 A04 A09 A11Survey footprint, holds, specialist work and residual information traceable.
BOUK-POL-COSHH
Hazardous substances and dust
R09
C09 C19
A05 A08 A11Products and generated dust assessed; effective source controls observed.

Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.

Management system coverage register 19 to 27

Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.

Policy requirement areaRisk and check linksAudit referencesImplementation evidence to test
BOUK-POL-NOISE
Occupational noise
R10
C10 C18
A05 A08 A11Exposure assessment, source reduction and required health arrangements evidenced.
BOUK-POL-VIB
Hand-arm and whole-body vibration
R11
C11 C18
A05 A08 A11Tools and real duration match assessment; escalation and surveillance referrals work.
BOUK-POL-MAN
Manual handling and ergonomics
R12
C12
A04 A05 A08 A11Handling design, aids and access reduce the task demand observed.
BOUK-POL-FIRE
Fire and hot work
R15
C15 C20
A04 A07 A10 A11Site/occupied-interface fire assessment, hot-work control and escape routes work.
BOUK-POL-CONF
Confined spaces
R16
C16
A01 A03 A10 A11No-entry assumption checked; change requires competent method and rescue before entry.
BOUK-POL-PTW
Permit to work and isolation
R17
C14 C17 C25
A04 A07 A10 A11Authorised permit and energy-isolation trail corresponds to physical boundaries.
BOUK-POL-TRAF
Traffic, logistics and public protection
R02
C02
A03 A04 A10 A11Logistics plan, segregation and public boundary work during actual movements.
BOUK-POL-OCC
Occupational health
R18
C18
A05 A08 A11Exposure-to-referral process and fitness restrictions checked without clinical disclosure.
BOUK-POL-PPE
Personal protective equipment
R19
C19
A05 A08 A11Suitability, fit, compatibility and maintenance evidenced; stronger controls retained.

Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.

Management system coverage register 28 to 35

Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.

Policy requirement areaRisk and check linksAudit referencesImplementation evidence to test
BOUK-POL-EMER
Emergency response and first aid
R20
C20
A04 A06 A10 A11Emergency cover, access, communication and specialist rescue verified by safe tests.
BOUK-POL-MON
Monitoring, audit and review
E04 R26
C01–C26
A01 A11 A12Planned versus actual coverage, evidence quality, independence and verification tested.
BOUK-POL-INC
Incident investigation
E04 R26
C26
A09 A11 A12Incident decisions, causal learning and corrective actions feed register changes.
BOUK-POL-WAT
Work near water and weather
R21
C21
A03 A06 A10 A11Water interfaces screened; weather thresholds and revised work decisions evidenced.
BOUK-POL-OFF
Office, display-screen and lone work
R22
C22
A01 A08 A11DSE, office and lone-working arrangements checked where work actually occurs.
BOUK-POL-DRV
Driving and travel for work
R23
C23
A08 A10 A11Journey/fatigue and vehicle arrangements sampled against actual business demand.
BOUK-POL-SPEC
Specialist and high-hazard interfaces
R25
C25
A02 A04 A07 A11Specialist boundaries and simultaneous operations have coordinated release ownership.
BOUK-POL-GAS
Gas safety and combustion equipment
R24
C24
A04 A07 A10 A11Specialist competence, work scope, isolation and commissioning records verified.

Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.

Findings escalation and verified improvement

Finding and immediate responseOwnership verification and closure
Critical control failureStop or restrict the affected activity immediately and notify Site Manager and Project Manager; escalate to Contracts Manager/H&S adviser the same shift. Restart needs competent technical acceptance and the person controlling the task to authorise it. No score overrides the hold.
Major system weaknessSite Manager sets containment before the next relevant exposure. Project Manager agrees the corrective plan, owner and due date within two working days; H&S adviser challenges adequacy. These are example company targets.
Other improvementAssign an owner and risk-proportionate due date at the closing meeting. Do not relabel a control failure as an observation to avoid action.
Implementation versus effectivenessRetain the completion evidence, then a separate test in representative work with verifier, date, result and limitations. The verifier must be competent and free from the conflict identified. Reopen ineffective changes and revise the risk register.
Overdue or repeated findingEscalate the actual risk and restriction. Contracts Manager agrees resources or a justified revised response; keep the original due date/history. Unresolved critical exposure remains held.

Worked example of a risk to assurance trail

S03 register R02 identifies reversing vehicles near pedestrians. C02 requires a delivery-time observation. A quiet weekly route check records no obstruction, but the March manager observation finds the protected route blocked during unloading. The manager stops that unloading arrangement and assigns a revised physical route and booking sequence to the Site Manager. A03 checks the cause, coordination and other affected workfaces. Closure requires two representative delivery observations on different days with the revised barrier and marshal arrangement working; photos alone do not establish continued effectiveness. This is a fictional worked finding, not an actual completed inspection.

Keep the finding linked to R02, C02, A03 and the action ID throughout. If a later observation finds pedestrians entering the reversing area, reopen the action, maintain the restriction and increase manager sampling until competent review supports the revised frequency.

Capacity reporting and plan review

Each active site reserves a 45-minute manager field inspection every week, plus 90 minutes each month for the deeper focus and evidence review. Additional direct observations of every active P1 work package, incident response and specialist checks are resourced separately. Supervisors build task checks into the shift plan. Audit allocations total 23.0 auditor-days before follow-up; the Contracts Manager provides competent cover so delivery duties cannot displace them.

MeasureRequired interpretation and response
Task coverageActive work packages mapped to register risk and check IDs / all active packages. Target 100%; unknown or unmapped work is held. Reconcile against the weekly lookahead, not the assurance log alone.
Check coverage and qualityDue checks with usable location/task/evidence/result records / checks due. Report missing checks separately from control failures. A completed form is not automatically a successful check.
P1 management observationActive P1 packages directly observed this month / all active P1 packages. Explain unavailable activities and book the next safe observation; never record a desk review as a field visit.
Audit and system coverageAudits performed / audits due, plus requirement areas actually tested / applicable areas planned. Report scope gaps, independence limits and changes; 35 planned domains are not 35 passed domains.
Action effectivenessCritical/major findings open or overdue, repeat failures, and implemented actions awaiting verification. Review risk and restrictions rather than rewarding a low reported finding count.
Health and learningExposure-control failures, surveillance referral exceptions and worker concerns through authorised aggregate records. Protect clinical information and do not use low incident numbers as proof of control.

The H&S adviser reviews delivery and new risk information monthly with the Contracts Manager. Project Managers confirm the work forecast, overdue findings and specialist capacity. The board receives quarterly trends and an immediate escalation for material failures. A12 sets the next annual programme using risk, work phases, legal change, worker feedback, incidents and verified audit outcomes.

Adapting this completed example

Replace the invented portfolio with current sites and dates, populate and validate the actual risk register, map every live package, confirm competent owners and check frequencies, verify the management-system requirements, resource the visits and obtain genuine approval. Retain blank inspection, audit and action records for actual results. Do not copy the worked finding or mark planned checks completed.

Further reading

HSE Managing health and safety — https://www.hse.gov.uk/managing/introduction/how-to-manage.htm

HSE HSG65 Managing for health and safety — https://www.hse.gov.uk/pubns/books/hsg65.htm

HSE Leadership check and audit — https://www.hse.gov.uk/leadership/plan-do-check-act/check.htm

Primary guidance checked 23 October 2026. Great Britain example; confirm project-specific and Northern Ireland requirements separately. Frequencies and deadlines in this plan are fictional company arrangements and do not replace applicable statutory or specialist requirements.

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.