Completed example for January to December 2027 | BOUK-PLN-MON-01 | Version 2.2 | 23 October 2026
FICTIONAL WORKED PLAN — BuildOut is the SHAREhub example business. The four named sites, work phases, risk inputs and programme below are invented. Checks and audits are planned, not completed; no real findings, signatures or approvals are claimed.
We will assure every active work package through supervisor checks, site-manager challenge and a separate risk-based audit programme. The 12-month plan connects the site portfolio, risk inputs R01–R26, activity checks C01–C26 and formal audits A01–A12, including A06B. A failed critical control stops the affected work regardless of an overall score or calendar date.
| Plan control | Completed example arrangement |
|---|---|
| Scope | Commercial refurbishment, retail fit out, light industrial construction and residential development. About 50 direct employees and 50–150 subcontract workers across changing projects. |
| Plan owner and sponsor | Competent H&S adviser maintains the programme. Contracts / Operations Manager owns delivery capacity. Managing Director / board sponsors resources and escalation. |
| Operating period | 1 January–31 December 2027. Baseline planning snapshot: 1 January 2027. Monthly review and immediate replan after material change. |
| Delivery model | Trade Supervisor checks every live task. Site Manager makes weekly site checks and monthly risk-focused observations. Competent reviewers conduct the formal audits. |
| Linked management system | Existing example policy and document register for Build Out UK Limited. Covers all 35 policy areas and their 271 listed management documents through the domain-to-audit mapping. |
| Adoption and approval | Prepared example only. Local scope, people, resources and technical arrangements require genuine review and authorisation before use. No signature is prefilled. |
How to use the plan
Start with the site portfolio, then use the risk/check catalogue to select every applicable control check. Follow the monthly additional focus and audit programme without dropping the standing checks. Use the final coverage register to identify the policy, procedure, assessment, permit or record to examine. Keep actual results and approvals in separate blank operational records.
Current example sites and work phases
These are the four active sites in this worked planning scenario, not a list of BuildOut’s actual live projects. ALL in the catalogue means S01 Jan–Sep, S02 Jan–Jun and S03/S04 Jan–Dec. HQ denotes company support processes, with no invented office address. Dates are planned phases and must move when the construction programme changes.
| Site and period | Work and exposure profile | Accountability |
|---|---|---|
| S01 Eastfield commercial refurbishment Jan–Sep | Jan–Feb surveys and strip out; Feb–Apr structural alterations; Apr–Jul services; Aug–Sep finishes and handover. Occupied neighbour interface throughout. Principal register inputs: R01–R05, R07–R15, R17–R20, R23–R26 | Site Manager S01; Project Manager S01 |
| S02 Harbour retail fit out Jan–Jun | Jan–Apr evening fit out beside trading areas; May commissioning; Jun handover. Client evacuation and out-of-hours interfaces are critical. Principal register inputs: R01–R04, R08–R20, R23–R26 | Site Manager S02; Project Manager S02 |
| S03 Foundry light industrial build Jan–Dec | Jan–Apr groundworks; Apr–Jul frame; Jun–Aug roof; Aug–Oct services; Oct–Dec fit out. Lifting and temporary stability require stage checks. Principal register inputs: R01–R06, R09–R15, R17–R21, R23–R26 | Site Manager S03; Project Manager S03 |
| S04 Meadow residential development Jan–Dec | Jan–Jun groundworks; Apr–Sep frames and roofs; Jul–Dec fit out. Concurrent trades, deliveries and changing public boundaries. Principal register inputs: R01–R06, R09–R15, R17–R21, R23–R26 | Site Manager S04; Project Manager S04 |
Site changes and demobilisation
Each Site Manager checks the next eight weeks of work every Friday with Trade Supervisors and the Project Manager. Add new activities, risks and specialist interfaces before they enter the work programme. The H&S adviser updates this plan within two working days of an accepted change; affected work remains held while essential controls are unresolved. These are company-set example planning times, not statutory deadlines.
S02 closes in June and S01 in September. Their audits and critical action verification occur before handover. Archive the final register, survey restrictions, design information and client transfer evidence. November can review those records but cannot retrospectively observe controls at a closed site. Any follow-on or reopened site needs a fresh mobilisation review.
Risk basis roles and minimum check frequency
The risk inputs are an original populated example, using the activity, hazard, controls, owner and evidence logic of the existing construction register. P1–P3 set assurance intensity; they are planning priorities, not numerical risk acceptance bands or permission to work. Scores and residual-risk decisions belong in the site’s competent task assessment.
| Priority | Supervisor responsibility | Site Manager responsibility |
|---|---|---|
| P1 serious acute or latent harm | Check every active workface before work and after change; verify each critical stage before release. Observe controls during the task and record the result each shift. | Weekly field check at every active site and at least one direct monthly observation of each active P1 work package; increase sampling after failure or change. |
| P2 significant recurring exposure | Check before the task and when conditions change. Complete one structured recorded sample per active trade each week, including actual duration and exposure controls. | Monthly sample of each active P2 activity, with different trades or shifts where practicable; check required specialist evidence. |
| P3 lower-consequence routine work | Check on first use and after change. Review worker-reported defects promptly and record the applicable local checks. | Monthly representative office/support sample; individual adjustment or defect actions remain separately tracked. |
The Site Manager’s weekly inspection is a separate challenge of current work, not a substitute for supervisors’ task checks. The monthly focus adds depth and changes the observation time or workface. Specialist examinations, statutory inspections, exposure monitoring and health surveillance retain their own competent methods and required intervals. This assurance calendar does not replace them.
Enduring risks to the business
| Register input | Assurance response |
|---|---|
| E01 weak ownership or insufficient resources | Contracts Manager reviews workload and cover monthly; A01 tests readiness and A12 resources the next year. Unstaffed critical checks prevent the affected release. |
| E02 unsuitable contractors or competence | C26 and A08 trace procurement through actual delivery, subcontracting and supervision. A11 challenges independence and consistency. |
| E03 stale design or task information | C26 and A01/A09 test version control and changed work. A new or changed task is mapped before work starts. |
| E04 misleading assurance or repeated failure | A11 tests coverage and evidence quality; A12 reviews recurrence and action effectiveness. Missing evidence is reported, never converted into a pass. |
Risk register inputs and activity checks 1 to 7
Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.
| Risk and priority | Activity check and evidence | Where and when | Audit links |
|---|---|---|---|
| R01 P2 Site establishment and welfare C01 | Inspect access, welfare, housekeeping and workface layout; compare the current construction phase plan with the shift. | ALL | A01 A04 A10 |
| R02 P1 Vehicle and public interfaces C02 | Observe a real delivery and separated pedestrian route; verify barriers, marshal positions and safe waiting arrangements. | ALL | A03 A04 A10 |
| R03 P1 Falls and dropped objects C03 | Verify edge protection, openings, safe access and falling-object controls at each live workface; record scaffold or access reference. | S01 Feb–Sep; S02 Jan–Apr; S03 Apr–Dec; S04 Apr–Dec | A02 A06 A10 |
| R04 P1 Lifting operations C04 | Match lift plan, people, equipment evidence, ground support and exclusion to the actual lift; witness critical-stage release. | S01 Feb–Apr; S02 Jan–Apr; S03 Apr–Aug; S04 Feb–Sep | A03 A06 A11 |
| R05 P1 Temporary works and stability C05 | Trace design, check category, loading restrictions, installation inspection and permit to load or dismantle to the installed works. | S01 Feb–Apr; S03 Jan–Aug; S04 Jan–Sep | A02 A03 A06 |
| R06 P1 Excavation collapse and services C06 | Match service information and detection to excavation; verify support, access, exclusion and competent inspection evidence before entry. | S03 Jan–Apr; S04 Jan–Jun | A03 A06 A10 |
| R07 P1 Demolition and structural alteration C07 | Verify survey and design scope, sequence, isolation, stability and exclusion before each structural stage; stop unassessed changes. | S01 Jan–Apr | A02 A09 A11 |
Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.
Risk register inputs and activity checks 8 to 14
Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.
| Risk and priority | Activity check and evidence | Where and when | Audit links |
|---|---|---|---|
| R08 P1 Asbestos disturbance C08 | Check exact task footprint against survey scope and exclusions; no intrusive release for unknown material or missing specialist handback. | S01 Jan–Jul; S02 Jan–Apr | A02 A04 A09 |
| R09 P1 Dust and hazardous substances C09 | Observe cutting, mixing or application; verify source control, extraction or wet method, suitable RPE and task assessment. | ALL while exposure tasks run | A05 A08 A11 |
| R10 P2 Noise exposure C10 | Compare actual tools, duration and nearby people with exposure assessment; check quieter method, segregation and protection. | ALL while noisy work runs | A05 A08 A11 |
| R11 P2 Vibration exposure C11 | Verify tool choice, maintenance, actual trigger-time recording and assessment; investigate changed duration or symptoms confidentially. | ALL while vibrating tools run | A05 A08 A11 |
| R12 P2 Manual handling and ergonomics C12 | Observe delivery-to-use handling; verify mechanical aids, load and route design and team capability against the task. | ALL | A04 A05 A08 |
| R13 P1 Plant and powered tools C13 | Observe guarding, isolation, condition and authorised use; match equipment inspection or maintenance evidence to asset ID. | ALL | A03 A06 A10 |
| R14 P1 Electrical installation and isolation C14 | Verify supply protection, condition and authorised isolation with a competent person; inspect evidence of dead-working controls and handback. | ALL; commissioning S01 Jul, S02 May, S03 Oct, S04 Oct–Dec | A04 A07 A10 |
Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.
Risk register inputs and activity checks 15 to 20
Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.
| Risk and priority | Activity check and evidence | Where and when | Audit links |
|---|---|---|---|
| R15 P1 Fire and hot work C15 | Check occupied routes, combustible control, permit precautions and the risk-assessed fire-watch arrangements; never use a universal watch duration. | ALL; hot work only under authorised method | A04 A07 A10 |
| R16 P1 Confined-space work C16 | Screen for confined spaces before each new package. If entry becomes necessary, require specialist assessment, isolation and practicable rescue. | No entry planned. All sites screen every lookahead; entry hold remains until authorised. | A01 A03 A10 |
| R17 P1 Permits and hazardous-energy isolation C17 | Trace one live permit from task scope to physical isolation, interfaces, shift handover and cancellation; verify authorised roles. | ALL where permits apply | A04 A07 A10 |
| R18 P2 Occupational health and fitness C18 | Check exposure-to-surveillance referral and fitness restrictions through authorised summaries; do not include diagnoses in shared logs. | ALL and company support | A05 A08 A11 |
| R19 P2 PPE and RPE suitability C19 | Confirm equipment selection, compatibility, condition and required face-fit evidence against the actual task; observe correct use. | ALL where required | A05 A08 A11 |
| R20 P1 Emergency response and first aid C20 | Check current access, alarm, first-aid cover and task rescue capability; test arrangements safely after layout or staffing changes. | ALL; exercises Mar and Oct at each active site | A04 A06 A10 |
Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.
Risk register inputs and activity checks 21 to 26
Each C-number is a defined checklist topic, not a completed result. Apply the P1–P3 frequency above to every active site and work package within the stated scope. Trade Supervisors own the task checks; Site Managers own the management sample. Specialists support checks requiring specialist competence.
| Risk and priority | Activity check and evidence | Where and when | Audit links |
|---|---|---|---|
| R21 P1 Weather and work near water C21 | Check forecast, ground and structural conditions against task limits. Screen water interfaces; no water work planned without separate assessment. | S03 S04 all year; S01 S02 where external work changes | A03 A06 A10 |
| R22 P3 Office DSE and lone working C22 | Check workstation changes, lone-work contact arrangements and safe access; verify adjustment actions with the worker. | HQ all year; each active site office | A01 A08 A11 |
| R23 P2 Driving and work travel C23 | Sample journey planning, fatigue arrangements, vehicle condition and driver authorisation; challenge deadlines causing unsafe travel. | ALL and company support | A08 A10 A11 |
| R24 P1 Gas and combustion equipment C24 | Screen use and installation; verify competent specialist, isolation, ventilation and commissioning evidence before acceptance. | S02 May; S01 Jul; S03 Oct; S04 Oct–Dec; no unplanned use | A04 A07 A10 |
| R25 P1 Specialist and simultaneous work C25 | Compare adjacent trades and client operations with the coordination plan; confirm one interface owner, boundaries and change release. | ALL; occupied interface S01 S02 | A02 A04 A07 |
| R26 P1 Unassessed task or control change C26 | Match every work package to register risks, current RAMS, competent supervisor and worker briefing; hold unmapped or changed work. | ALL and each new subcontract package | A01 A08 A11 |
Stop or hold when a critical prerequisite fails, the work exceeds the defined scope or material information is missing. Record the actual area, package, date, shift, assessor, evidence reference and response; a tick without these links does not establish coverage.
Twelve month activity checklist schedule January to June
Standing programme in every active month: supervisors check all current tasks under C01–C26 as applicable; Site Managers complete the weekly inspection and monthly P1/P2 observations. The additional focus below deepens that work. It must not become the only task checked that month.
| Month and active sites | Additional risk based focus | Manager observation and evidence | Formal audit |
|---|---|---|---|
| Jan S01 S02 S03 S04 | C01 C02 C08 C26 | Verify every live package is mapped before mobilisation; S01/S02 survey gaps held; S03/S04 groundworks releases checked. | A01 |
| Feb S01 S02 S03 S04 | C03 C05 C07 C08 C25 | S01 structure and asbestos boundaries; S03/S04 ground conditions; observe changed occupied interfaces at S02. | A02 |
| Mar S01 S02 S03 S04 | C02 C06 C13 C20 C21 | Sample an excavation and busy delivery at each relevant site; safe emergency exercise at all four active sites. | A03 |
| Apr S01 S02 S03 S04 | C03 C04 C05 C15 C17 | Observe critical frame/lift stages at S03/S04 and evening occupied-fit-out permits/fire precautions at S02. | A04 |
| May S01 S02 S03 S04 | C09 C10 C11 C12 C18 C19 | Compare exposure controls with observed tools and duration; include subcontractors and sensitive health referrals without clinical detail. | A05 |
| Jun S01 S02 S03 S04 | C03 C04 C05 C20 C26 | S04 frame/rescue checks; S02 commissioning and all critical closeout actions checked before its June handover. | A06 A06B |
Monthly delivery record
By the fifth working day of the following month, each Site Manager reconciles the task register with recorded checks, including evening work, subcontractors and work after layout changes. Record missing checks as exceptions with an owner and response. Confirm all active P1 work packages received direct manager observation; report any safe-observation limitation and the alternative evidence agreed.
Twelve month activity checklist schedule July to December
Standing programme in every active month: supervisors check all current tasks under C01–C26 as applicable; Site Managers complete the weekly inspection and monthly P1/P2 observations. The additional focus below deepens that work. It must not become the only task checked that month.
| Month and active sites | Additional risk based focus | Manager observation and evidence | Formal audit |
|---|---|---|---|
| Jul S01 S03 S04 | C14 C15 C17 C24 C25 | S01 services handback and gas interface; S03 roof boundaries; S04 frame-to-fit-out interfaces. | A07 |
| Aug S01 S03 S04 | C09 C12 C18 C22 C23 C26 | Check new subcontract packages and competence, heat/fatigue and consultation; test one register change at each active site. | A08 |
| Sep S01 S03 S04 | C01 C08 C14 C17 C26 | S01 final restrictions and residual risks transferred before closure; verify S03/S04 phase changes and live work scope. | A09 |
| Oct S03 S04 | C02 C15 C20 C21 C24 | Both sites repeat winter, access and fire checks after layout changes; safe emergency exercise and specialist commissioning checks. | A10 |
| Nov S03 S04 plus HQ | C01–C26 as applicable | Independent system audit tests all policy domains. Managers produce open-risk and missed-check lists without pre-filling results. | A11 |
| Dec S03 S04 plus HQ | C20 C21 C23 C26 | Verify outstanding actions before shutdown/restart arrangements; confirm future phases, new risks and 2028 coverage. | A12 |
Monthly delivery record
By the fifth working day of the following month, each Site Manager reconciles the task register with recorded checks, including evening work, subcontractors and work after layout changes. Record missing checks as exceptions with an owner and response. Confirm all active P1 work packages received direct manager observation; report any safe-observation limitation and the alternative evidence agreed.
Formal site and system audit programme January to May
Formal audits test how site-wide arrangements produce effective controls. They include records, interviews and work observation and are separate from routine inspections. Auditors must be competent and sufficiently independent of the work they assess; a peer review’s limitations are declared. Days below are example resource allocations and increase if coverage cannot be achieved.
| Audit month and scope | Risk and system focus | Lead resource and minimum sample |
|---|---|---|
| A01 Jan HQ plus mobilisation review at all sites | Governance, legal schedule, CDM appointments, design risk, register completeness and readiness. E01–E04; R01 R16 R22 R26. | H&S adviser with Contracts Manager and Design Manager; 2 auditor-days Four project baselines, one design-change trail per site, complete risk-to-task map. Escalate missing prerequisites before work. |
| A02 Feb S01 full site audit | Strip out, asbestos boundaries, structural alteration, temporary works and occupied interface. R03 R05 R07 R08 R25. | H&S adviser plus competent structural/asbestos input; 1.5 days All live critical fronts and their release records; interview two supervisors and three workers; trace every open high-risk hold. |
| A03 Mar S03 full site audit; S04 comparison | Groundworks, services, lifting set-up, plant, weather and emergency arrangements. R02 R04 R05 R06 R13 R16 R21. | Peer Project Manager and competent H&S adviser; 1.5 days Observe one excavation and delivery at each active sample; compare three permit/inspection records; test drawing-to-workface match. |
| A04 Apr S02 full site and client interface audit | Occupied retail fit out, survey scope, fire, electrical work, permits and contractor control. R01 R02 R08 R12 R14 R15 R17 R20 R24 R25. | Independent peer Site Manager with H&S adviser; 2 days Cover an evening shift, client handover and one live controlled task. Test all applicable site-system domains in the coverage register. |
| A05 May S01 and S04 field visits; all-site records | Dust, COSHH, noise, vibration, handling, RPE and occupational-health arrangements. R09 R10 R11 R12 R18 R19. | Competent occupational hygienist/adviser and H&S adviser; 2 days Observe at least one highest-exposure task per visited site; review assessment and monitoring representativeness at all four sites. |
Formal site and system audit programme June to August
Formal audits test how site-wide arrangements produce effective controls. They include records, interviews and work observation and are separate from routine inspections. Auditors must be competent and sufficiently independent of the work they assess; a peer review’s limitations are declared. Days below are example resource allocations and increase if coverage cannot be achieved.
| Audit month and scope | Risk and system focus | Lead resource and minimum sample |
|---|---|---|
| A06 Jun S04 full site audit | Frames, lifting, temporary works, work at height and rescue. R03 R04 R05 R06 R13 R20 R21. | Peer Project Manager and competent lifting/temporary-works reviewers; 1.5 days All live critical-stage releases; one installed system back to design and inspection; interview different trades. |
| A06B Jun S02 closeout before demobilisation | Outstanding actions, client handback, commissioning and residual risks. R08 R14 R15 R17 R20 R24 R25. | H&S adviser independent of S02 delivery; 0.5 day All critical actions and client restrictions. Preserve evidence for A11; do not defer closeout to the November review. |
| A07 Jul S01 full site pre-handover audit | MEP isolation, testing, gas specialist interface, permits and occupied-building handback. R14 R15 R17 R24 R25. | Peer Project Manager plus competent services reviewer; 1 day One complete isolation-to-reinstatement trail and all safety-critical commissioning exceptions; test current site-wide controls. |
| A08 Aug HQ with S03 and S04 site samples | Procurement, subcontractors, competence, consultation, health, fatigue, driving and change. E01 E02 E03; R09–R12 R18 R19 R22 R23 R26. | H&S adviser with Procurement and People coordinators; 2 days Two contractor packages per visited site, agency/apprentice briefing where present, one concern through to response and one changed work package. |
Formal site and system audit programme September to December
Formal audits test how site-wide arrangements produce effective controls. They include records, interviews and work observation and are separate from routine inspections. Auditors must be competent and sufficiently independent of the work they assess; a peer review’s limitations are declared. Days below are example resource allocations and increase if coverage cannot be achieved.
| Audit month and scope | Risk and system focus | Lead resource and minimum sample |
|---|---|---|
| A09 Sep S01 closeout and project learning | Handover, residual hazards, design changes and verified actions. R07 R08 R26; E03 E04. | Contracts Manager and H&S adviser outside S01 action ownership; 1 day All critical actions, representative major actions and the final client information transfer. Preserve evidence for A11. |
| A10 Oct S03 and S04 full site audits | Changed phases, winter readiness, fire, traffic, electrical/gas work, permits and emergencies. R01–R06 R13–R17 R20 R21 R23–R25. | Cross-project H&S/engineering audit team; 3 auditor-days Separate site reports; cover current work fronts, one delivery and one emergency communication test at each site; earlier-domain checks revisited. |
| A11 Nov HQ and S03/S04; S01/S02 archived evidence | Independent management-system implementation audit across all 35 policy areas and their subordinate requirements. E01–E04; R01–R26. | Independent competent auditor not owning the assessed controls; 4 auditor-days Risk-led samples plus 100% domain coverage. Closed-site conclusions use retained records and state the absence of current field observation. |
| A12 Dec HQ board review and S03/S04 follow-up | Compliance evaluation, audit gaps, action effectiveness, objectives and the next annual plan. E01–E04; all unresolved risks. | Managing Director/board with H&S adviser; 1 day plus follow-up All critical/overdue findings, incomplete domain coverage, worker concerns, exposure trends and justified resources for the next year. |
Detailed audit plan for A03 groundworks and site controls
Objective: determine whether S03’s management arrangements keep excavation, service and plant controls effective during real work, then compare a targeted S04 sample. The peer Project Manager leads; the H&S adviser and competent excavation/services reviewer support technical judgements. The delivery manager cannot independently verify their own disputed finding.
| Audit stage | Planned test and evidence |
|---|---|
| Before the visit | Obtain the current register, construction phase plan, task inventory, legal schedule, design/service information, permits, inspection records, competence evidence and prior actions. Confirm activity timings and a safe observation position. |
| 09:00–09:30 opening | Confirm scope, criteria, live operations, restrictions, worker participation and reporting route. Identify inaccessible areas and evidence not yet available. |
| 09:30–11:30 field observation | At S03 observe one live excavation workface, one plant/pedestrian interface and one controlled service-crossing task if safely active. Compare actual boundaries, access and equipment to the method. Stop and escalate an ineffective critical control immediately. |
| 11:30–12:30 evidence trail | Trace three excavation/permit/inspection records across more than one day. Select at least one changed work package. Verify reference, scope, competent role and whether the recorded condition matches the workface. |
| 13:00–14:00 people and system | Interview the Site Manager, two supervisors and three workers across trades. Test understanding, consultation, induction, subcontractor coordination, welfare and emergency access; attendance alone is insufficient. |
| 14:00–15:00 follow-through | Trace all open critical findings and two purportedly closed major actions. Check the physical outcome and the effectiveness test, with remaining limitations. Check design/change control and current document versions. |
| 15:00–16:00 conclusions | Distinguish observed fact, missing evidence and inference. Agree containment, owners, deadlines and verification criteria; the audited manager may dispute facts with evidence but cannot remove an unresolved finding. |
| Second site and reporting | Use the remaining half-day for S04 comparison and report completion. Expand the scope or add time if significant differences or gaps appear. Issue a scoped report within five working days; critical findings are communicated immediately. |
Sample sizes are minimum starting points. Add samples for contradictory evidence, high turnover or repeated failure. An unavailable critical activity is not marked passed: record the limitation and schedule an observation before or during its next safe occurrence. The report states what the sample does and does not establish.
Management system coverage register 1 to 9
Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.
| Policy requirement area | Risk and check links | Audit references | Implementation evidence to test |
|---|---|---|---|
| BOUK-HS-001 Health and safety management | E01 E04 C26 | A01 A11 A12 | Policy intent, role authority, resources and arrangements traced into site decisions. |
| BOUK-POL-GOV Leadership and document control | E01 E03 E04 C26 | A01 A11 A12 | Controlled issue, legal change, objectives and board decisions reach current site instructions. |
| BOUK-POL-CDM CDM project delivery | E01 E02 E03 R26 C01 C25 C26 | A01 A04 A09 A11 | Appointments, construction phase plan and handover follow actual dutyholder scope. |
| BOUK-POL-DES Design risk management | E03 R05 R07 R26 C05 C07 C26 | A01 A02 A09 A11 | Design hazards, residual information and revisions match installed and altered work. |
| BOUK-POL-RISK Risk assessment and RAMS | E03 R01–R26 C01–C26 | A01 A08 A11 | All live tasks mapped; assessment and method changes briefed and controlled. |
| BOUK-POL-COMP People and competence | E01 E02 R26 C26 | A01 A08 A11 | Task competence, authorisation, supervision and absence cover evidenced at work. |
| BOUK-POL-CONS Worker consultation | E04 R26 C26 | A08 A11 A12 | Workers and subcontractors influence controls; a concern has a recorded response. |
| BOUK-POL-SUB Contractors and procurement | E02 R25 R26 C25 C26 | A04 A08 A11 | Procurement evidence and subcontracted scope match the actual method and interfaces. |
| BOUK-POL-WEL Site establishment and welfare | R01 C01 | A04 A10 A11 | Welfare, work environment and changing site access inspected against use. |
Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.
Management system coverage register 10 to 18
Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.
| Policy requirement area | Risk and check links | Audit references | Implementation evidence to test |
|---|---|---|---|
| BOUK-POL-WAH Work at height | R03 C03 | A02 A06 A10 A11 | Edge/opening/access and falling-object controls verified at live workfaces. |
| BOUK-POL-LIFT Lifting operations | R04 C04 | A03 A06 A11 | Lift planning and competent roles traced to equipment, ground and exclusion. |
| BOUK-POL-PLANT Plant and work equipment | R13 C13 | A03 A06 A10 A11 | Equipment procurement, maintenance, inspection and safe isolation match assets. |
| BOUK-POL-ELEC Electrical safety | R14 C14 C17 | A04 A07 A10 A11 | Electrical competence, isolation and test evidence support safe reinstatement. |
| BOUK-POL-TW Temporary works and stability | R05 C05 | A02 A03 A06 A11 | Temporary-works design, check, inspection and release chain preserved. |
| BOUK-POL-EXC Excavations and buried services | R06 C06 | A03 A06 A11 | Service detection, support and competent inspection correspond to excavation. |
| BOUK-POL-DEM Demolition and structural alteration | R07 C07 | A02 A09 A11 | Structural survey, sequence, stability and exclusion reflected in stage releases. |
| BOUK-POL-ASB Asbestos | R08 C08 | A02 A04 A09 A11 | Survey footprint, holds, specialist work and residual information traceable. |
| BOUK-POL-COSHH Hazardous substances and dust | R09 C09 C19 | A05 A08 A11 | Products and generated dust assessed; effective source controls observed. |
Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.
Management system coverage register 19 to 27
Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.
| Policy requirement area | Risk and check links | Audit references | Implementation evidence to test |
|---|---|---|---|
| BOUK-POL-NOISE Occupational noise | R10 C10 C18 | A05 A08 A11 | Exposure assessment, source reduction and required health arrangements evidenced. |
| BOUK-POL-VIB Hand-arm and whole-body vibration | R11 C11 C18 | A05 A08 A11 | Tools and real duration match assessment; escalation and surveillance referrals work. |
| BOUK-POL-MAN Manual handling and ergonomics | R12 C12 | A04 A05 A08 A11 | Handling design, aids and access reduce the task demand observed. |
| BOUK-POL-FIRE Fire and hot work | R15 C15 C20 | A04 A07 A10 A11 | Site/occupied-interface fire assessment, hot-work control and escape routes work. |
| BOUK-POL-CONF Confined spaces | R16 C16 | A01 A03 A10 A11 | No-entry assumption checked; change requires competent method and rescue before entry. |
| BOUK-POL-PTW Permit to work and isolation | R17 C14 C17 C25 | A04 A07 A10 A11 | Authorised permit and energy-isolation trail corresponds to physical boundaries. |
| BOUK-POL-TRAF Traffic, logistics and public protection | R02 C02 | A03 A04 A10 A11 | Logistics plan, segregation and public boundary work during actual movements. |
| BOUK-POL-OCC Occupational health | R18 C18 | A05 A08 A11 | Exposure-to-referral process and fitness restrictions checked without clinical disclosure. |
| BOUK-POL-PPE Personal protective equipment | R19 C19 | A05 A08 A11 | Suitability, fit, compatibility and maintenance evidenced; stronger controls retained. |
Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.
Management system coverage register 28 to 35
Each policy area below covers its subordinate procedures, assessments, permits and records. All 35 areas and 271 listed documents have a parent-domain audit route. Many documents are planned: test implementation and record missing controls as findings.
| Policy requirement area | Risk and check links | Audit references | Implementation evidence to test |
|---|---|---|---|
| BOUK-POL-EMER Emergency response and first aid | R20 C20 | A04 A06 A10 A11 | Emergency cover, access, communication and specialist rescue verified by safe tests. |
| BOUK-POL-MON Monitoring, audit and review | E04 R26 C01–C26 | A01 A11 A12 | Planned versus actual coverage, evidence quality, independence and verification tested. |
| BOUK-POL-INC Incident investigation | E04 R26 C26 | A09 A11 A12 | Incident decisions, causal learning and corrective actions feed register changes. |
| BOUK-POL-WAT Work near water and weather | R21 C21 | A03 A06 A10 A11 | Water interfaces screened; weather thresholds and revised work decisions evidenced. |
| BOUK-POL-OFF Office, display-screen and lone work | R22 C22 | A01 A08 A11 | DSE, office and lone-working arrangements checked where work actually occurs. |
| BOUK-POL-DRV Driving and travel for work | R23 C23 | A08 A10 A11 | Journey/fatigue and vehicle arrangements sampled against actual business demand. |
| BOUK-POL-SPEC Specialist and high-hazard interfaces | R25 C25 | A02 A04 A07 A11 | Specialist boundaries and simultaneous operations have coordinated release ownership. |
| BOUK-POL-GAS Gas safety and combustion equipment | R24 C24 | A04 A07 A10 A11 | Specialist competence, work scope, isolation and commissioning records verified. |
Screen every area at each site. Document justified non-applicability and its change trigger. Each full site audit tests the relevant implementation; A11 reconciles all domains with the current management register.
Findings escalation and verified improvement
| Finding and immediate response | Ownership verification and closure |
|---|---|
| Critical control failure | Stop or restrict the affected activity immediately and notify Site Manager and Project Manager; escalate to Contracts Manager/H&S adviser the same shift. Restart needs competent technical acceptance and the person controlling the task to authorise it. No score overrides the hold. |
| Major system weakness | Site Manager sets containment before the next relevant exposure. Project Manager agrees the corrective plan, owner and due date within two working days; H&S adviser challenges adequacy. These are example company targets. |
| Other improvement | Assign an owner and risk-proportionate due date at the closing meeting. Do not relabel a control failure as an observation to avoid action. |
| Implementation versus effectiveness | Retain the completion evidence, then a separate test in representative work with verifier, date, result and limitations. The verifier must be competent and free from the conflict identified. Reopen ineffective changes and revise the risk register. |
| Overdue or repeated finding | Escalate the actual risk and restriction. Contracts Manager agrees resources or a justified revised response; keep the original due date/history. Unresolved critical exposure remains held. |
Worked example of a risk to assurance trail
S03 register R02 identifies reversing vehicles near pedestrians. C02 requires a delivery-time observation. A quiet weekly route check records no obstruction, but the March manager observation finds the protected route blocked during unloading. The manager stops that unloading arrangement and assigns a revised physical route and booking sequence to the Site Manager. A03 checks the cause, coordination and other affected workfaces. Closure requires two representative delivery observations on different days with the revised barrier and marshal arrangement working; photos alone do not establish continued effectiveness. This is a fictional worked finding, not an actual completed inspection.
Keep the finding linked to R02, C02, A03 and the action ID throughout. If a later observation finds pedestrians entering the reversing area, reopen the action, maintain the restriction and increase manager sampling until competent review supports the revised frequency.
Capacity reporting and plan review
Each active site reserves a 45-minute manager field inspection every week, plus 90 minutes each month for the deeper focus and evidence review. Additional direct observations of every active P1 work package, incident response and specialist checks are resourced separately. Supervisors build task checks into the shift plan. Audit allocations total 23.0 auditor-days before follow-up; the Contracts Manager provides competent cover so delivery duties cannot displace them.
| Measure | Required interpretation and response |
|---|---|
| Task coverage | Active work packages mapped to register risk and check IDs / all active packages. Target 100%; unknown or unmapped work is held. Reconcile against the weekly lookahead, not the assurance log alone. |
| Check coverage and quality | Due checks with usable location/task/evidence/result records / checks due. Report missing checks separately from control failures. A completed form is not automatically a successful check. |
| P1 management observation | Active P1 packages directly observed this month / all active P1 packages. Explain unavailable activities and book the next safe observation; never record a desk review as a field visit. |
| Audit and system coverage | Audits performed / audits due, plus requirement areas actually tested / applicable areas planned. Report scope gaps, independence limits and changes; 35 planned domains are not 35 passed domains. |
| Action effectiveness | Critical/major findings open or overdue, repeat failures, and implemented actions awaiting verification. Review risk and restrictions rather than rewarding a low reported finding count. |
| Health and learning | Exposure-control failures, surveillance referral exceptions and worker concerns through authorised aggregate records. Protect clinical information and do not use low incident numbers as proof of control. |
The H&S adviser reviews delivery and new risk information monthly with the Contracts Manager. Project Managers confirm the work forecast, overdue findings and specialist capacity. The board receives quarterly trends and an immediate escalation for material failures. A12 sets the next annual programme using risk, work phases, legal change, worker feedback, incidents and verified audit outcomes.
Adapting this completed example
Replace the invented portfolio with current sites and dates, populate and validate the actual risk register, map every live package, confirm competent owners and check frequencies, verify the management-system requirements, resource the visits and obtain genuine approval. Retain blank inspection, audit and action records for actual results. Do not copy the worked finding or mark planned checks completed.
Further reading
HSE Managing health and safety — https://www.hse.gov.uk/managing/introduction/how-to-manage.htm
HSE HSG65 Managing for health and safety — https://www.hse.gov.uk/pubns/books/hsg65.htm
HSE Leadership check and audit — https://www.hse.gov.uk/leadership/plan-do-check-act/check.htm
Primary guidance checked 23 October 2026. Great Britain example; confirm project-specific and Northern Ireland requirements separately. Frequencies and deadlines in this plan are fictional company arrangements and do not replace applicable statutory or specialist requirements.