Ground-breaking, service verification and excavation inspection procedure

BOUK-PRO-EXC · v1.0 · Completed fictional example · DOCX

Plan survey and trial holes, support/batter excavations, inspect and coordinate permits.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PRO-EXC | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Plan survey and trial holes, support/batter excavations, inspect and coordinate permits.

Scope and operating responsibility

We apply this procedure to Drainage trench beside an occupied building. Evidence includes Service enquiry and locating; excavation assessment and permit where used; design/support details; inspections; emergency plan; backfill and reinstatement. The role controlling the task checks applicability before mobilisation and whenever the scope changes.

RoleRequired action
Site managerOwn this arrangement, confirm competent support and maintain its evidence trail.
Project manager and Site managerCoordinate the actual package, provide resources and verify prerequisites before release; resolve occupied and subcontractor interfaces.
Trade supervisor and workersUse the accepted current method, demonstrate understanding, report changes and stop when critical safeguards are uncertain.
Competent specialist and H&S adviserProvide technical advice within competence; challenge evidence and identify limitations. Management retains the operating decision.

Inputs before using the procedure

Use the current project risk register, relevant survey and design revisions, equipment or product information, worker consultation and the task-specific records listed below. Resolve conflicting or missing information before relying on it. Do not fill missing technical values from an example.

Guidance Excavations: ground, services and inspection · Buried services and safe excavation · HSE Excavations

How we carry out the arrangement

1 Plan and obtain reliable information

The Site Manager coordinates service information, site reconnaissance, competent locating and safe exposure before ground penetration. Plans alone do not prove the location, depth or status of a service.

2 Verify capability and prerequisites

A competent plan addresses support or battering, edge loading, spoil, access, people and plant separation, water, adjacent structures and possible hazardous atmospheres.

3 Control work and interfaces

The Site Manager arranges a competent inspection before work at the start of each shift, after an event likely to affect excavation strength or stability, and after material unintentionally falls or is dislodged. The inspector checks the excavation, supports, access, nearby equipment and materials from a safe position. Rain, changed loading or damaged support can require a fresh inspection; yesterday’s report does not release today’s work.

BuildOut requires a record of every inspection on BOUK-FRM-EXC-01 and delivery to the Site Manager before the shift ends. Unsafe findings are communicated immediately and affected work stays held until satisfactorily remedied and competently rechecked. Record the organisation and address, exact location and description, inspection time, findings, action taken, further action, inspector’s name and position, and report recipient and delivery time. Keep reports accessible on site until construction finishes and for at least three months afterwards, subject to any longer applicable retention requirement.

4 Review change and safe handback

Service-strike, collapse, flooding and rescue arrangements are established before excavation. Nobody enters an unstable excavation to attempt an improvised rescue.

Stop restrict and restart

Stop excavation or entry when service identity, stability, support, water, atmosphere, access or protective separation is uncertain or deteriorates.

The person controlling the work makes the affected area safe and notifies the Site Manager. Restart requires the competent technical decision for the actual control, the authorised work-release decision and a fresh briefing of affected people. Record unresolved limits; an updated date or a completed form does not remove a hold.

Practical control detail

A competent inspection tests whether the as-built trench still matches the approved support and access arrangement. If a change undermines that basis, stop entry, protect people at the edge and obtain a revised competent decision before restarting.

Wet ground, a new layer, edge cracking or changed loading can invalidate an earlier assessment. Protect people outside the affected area while competent reassessment establishes the next step.

Evidence follow up and learning

Worked decision trail

Fictional situationDecision and evidence
What changesRainwater and cracking appear beside an occupied trench.
ResponseThe supervisor withdraws people, protects the edge and refers support, water and loading conditions for competent reassessment.
VerificationA fresh competent inspection and any revised design are required before entry; pumping alone is not a release.

Supporting arrangement documents

ReferenceHow the document is used
BOUK-RA-EXC-01
Excavation, ground and service-strike assessment
Evaluate ground stability, services, water, access, plant loads and adjacent structures.
BOUK-PTW-EXC-01
Permit to dig and break ground
Confirm plans, locating/survey, trial holes, isolation/interfaces and work limits.
BOUK-RAMS-EXC-01
Excavation support, access and backfill RAMS
Set sequence, shoring/battering, edge protection, inspections and safe reinstatement.
BOUK-FRM-EXC-01
Excavation inspection and defect report
Record competent inspections, defects and safe-work restrictions.
BOUK-FRM-EXC-02
Utility detection, trial-hole and as-built record
Capture verified service position, limitations, markings and communicated changes.
BOUK-RAMS-EXC-02
Site clearance and shallow groundworks RAMS
Service discovery, vegetation, plant/public separation and changing ground conditions.
BOUK-RAMS-EXC-03
Piling and ground-improvement works RAMS
Ground-bearing platforms, rig stability, services, noise/vibration and exclusion interfaces.
BOUK-RAMS-EXC-04
Drainage and sanitary installation RAMS
Ground/services, biological exposure, handling, testing and confined-space screening.

Retain the record ID, task, location, competent author, revision, date, decision, restrictions, action owner and separate effectiveness evidence. Restrict personal and health information and apply the relevant retention rule. File genuine results separately from teaching examples.

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.