Temporary works design brief and check certificate

BOUK-FRM-TW-01 · v1.0 · Blank editable master · DOCX

Capture loads, assumptions, interfaces, design/check responsibilities and approval.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-FRM-TW-01 | Version 1.0 | 23 October 2026 | GB baseline

BLANK EDITABLE MASTER. Record actual facts, evidence and decisions. Operational entries, signatures and approvals are blank.

Capture loads, assumptions, interfaces, design/check responsibilities and approval.

Record identityActual entry
Record reference and project
Exact location task and date
Recorder role and competence

Scope facts and prerequisites

Required informationActual evidence or decision
Temporary works ID use duration and design brief
Loads ground supporting structure and sequence inputs
Design standard assumptions and interface information
Design category and required checking route
Designer and checker competence evidence

Decisions handover and verification

Hold loading, alteration or dismantling when a design, check, foundation, bracing, connection or sequence requirement is uncertain or no longer met.

Required informationActual evidence or decision
Design and check documents received separately
Outstanding assumptions restrictions and hold points
Accepted installation revision and distribution
Actual competent design acceptance and date
Finding or actionOwner and due dateEvidence and effectiveness
Review and acceptanceActual entry
Reviewer name role and date
Required signatures and date
Remaining restrictions and restart authority

Retain factual evidence and limitations. A signature, permit or tick does not establish that the physical controls work. Use the separate procedure and the completed decision example for guidance; never copy an example as an actual result.

Guidance Foundations of Construction Health and Safety Management · Scaffolding Safety