Provide suitable rescue arrangements and competent people before entry.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PLN-CONF-01 | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Provide suitable rescue arrangements and competent people before entry.

Example project context

This plan belongs to the fictional 2027 BuildOut portfolio: Eastfield commercial refurbishment, Harbour retail fit out, Foundry light-industrial build and Meadow residential development. Apply the stated arrangements only to the relevant task and phase. The example has no real site address, named staff or technical certification. Project-specific engineering, exposure and rescue information remains a prerequisite to genuine work release.

Plan controlCompleted example arrangement
Accountable roleAuthorised specialist / appointed person coordinates the plan and confirms competent deputies.
Activities and interfacesNon-entry recovery and specialist rescue provision
Risk and policy linkBOUK-POL-CONF and the current task register; map affected work packages before release.
Resources and timingProject manager confirms competent people, equipment, welfare, time and specialist input before the relevant phase. Site manager reviews the next eight weeks at weekly coordination.
Change routeChanged scope, equipment, sequence, people or site conditions reopen the affected plan and task release.

Delivery stages responsibilities and evidence

When and ownerCompleted arrangementEvidence required
Before appointment
Authorised specialist / appointed person
Avoid entry to service ducts, tanks, chambers and other confined spaces where the task can be completed without entry. A deep excavation is assessed for its conditions rather than labelled safe or confined from depth alone.Avoid-entry review; confined-space assessment; isolation and atmosphere evidence; entry authorisation; communication and rescue-readiness checks
Before mobilisation
Project manager and competent specialist
A competent assessment addresses specified risks, connections, isolation, atmosphere, ingress, access, work activity and people outside. Monitoring and ventilation must suit the actual hazard and method.Avoid-entry review; confined-space assessment; isolation and atmosphere evidence; entry authorisation; communication and rescue-readiness checks
At each relevant work stage
Site manager and Trade supervisor
Where entry is necessary, the supervisor verifies the safe system, competent team, communication and suitable rescue arrangements before authorisation; a permit alone does not make entry safe.Avoid-entry review; confined-space assessment; isolation and atmosphere evidence; entry authorisation; communication and rescue-readiness checks
After change or before handback
Site manager and competent reviewer
The rescue team and equipment must be available and capable for the space. Emergency services are contacted as necessary but are not the sole planned rescue provision.Avoid-entry review; confined-space assessment; isolation and atmosphere evidence; entry authorisation; communication and rescue-readiness checks

Hold points and safe release

Prohibit entry or withdraw if isolation, atmosphere, communication, monitoring, staffing or rescue readiness is not maintained.

At a failed prerequisite, the supervisor holds the affected work and protects people. The Site Manager records the boundary and communicates it to adjacent teams. The competent specialist resolves technical conditions; the authorised operating role checks implementation, briefs changes and records the release conditions. Recheck a later change rather than extending an expired acceptance automatically.

Specific plan arrangements

Entry avoidance

The example drainage survey uses remote inspection from a protected position outside the chamber. Entry is not planned or authorised. A proposed change to entry starts a fresh competent assessment.

Before necessary entry

If avoidance is not practicable, a competent specialist defines the actual space, specified risks, connections, isolation, atmosphere, access and rescue method. The task stays held until the team and equipment can deliver that method.

Team and readiness

Define entrant, attendant, supervisor, rescue roles and reliable communications. Verify monitoring, ventilation, personnel accounting and rescue availability at the actual space before any permit is accepted.

Alarm or casualty

The attendant raises the alarm and activates the accepted rescue and emergency response. Prevent unplanned entry by colleagues. Rescue personnel act only under the practised space-specific method and within competence.

Failure or changed conditions

Withdraw or prohibit entry on loss of atmosphere, isolation, communication or rescue readiness. A permit extension cannot resolve a failed physical control.

Closeout

Account for all people and equipment, retain isolations or restrictions as required and hand back through the authorised roles. This example contains no fabricated atmosphere readings or actual rescue rehearsal.

Practical application and review

Worked decision trail

Fictional situationDecision and evidence
What changesA drainage camera task is changed to proposed chamber entry.
ResponseEntry remains prohibited until a competent space-specific safe system, isolation, monitoring, team and rescue capability are established.
VerificationVerify those prerequisites at the space; a permit and a call to emergency services alone are insufficient.

Turn emergency response at work knowledge into a decision

An emergency response plan should tell people what to do for the incidents their workplace could face: raise the alarm, protect people, call help, isolate a hazard only when safe, and hand over to responders. Choose evacuation or shelter from the actual threat, include contractors and visitors, and test night-shift and changed-route conditions before relying on the plan. Retain the scenario, role checks, alarm test and improvement actions; retest any failed arrangement.

How should confined space risk assessment be carried out

Confined-space risk assessment should identify the space, the specified risks, the work activity, changing conditions, affected people and the controls needed before entry.

Assurance and update cycle

Supervisors check the controls before relevant work and after change. The Site Manager samples implementation during actual work; the H&S adviser challenges recurring gaps and the plan owner reviews the resulting evidence. Specialist and statutory inspections retain their own competent methods and required intervals. Actions need both completion evidence and a separate effectiveness check; reopen a failed change.

Related SHARE guidance

Guidance How should confined spaces be controlled? · Emergency response at work

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.