BOUK-PLN-LIFT-01 | Version 1.0 | 23 October 2026 | GB baseline
COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.
Define load, equipment, configuration, ground support, people, communications and exclusion zones.
Example project context
This plan belongs to the fictional 2027 BuildOut portfolio: Eastfield commercial refurbishment, Harbour retail fit out, Foundry light-industrial build and Meadow residential development. Apply the stated arrangements only to the relevant task and phase. The example has no real site address, named staff or technical certification. Project-specific engineering, exposure and rescue information remains a prerequisite to genuine work release.
| Plan control | Completed example arrangement |
|---|---|
| Accountable role | Authorised specialist / appointed person coordinates the plan and confirms competent deputies. |
| Activities and interfaces | Crane lift of rooftop air-handling equipment |
| Risk and policy link | BOUK-POL-LIFT and the current task register; map affected work packages before release. |
| Resources and timing | Project manager confirms competent people, equipment, welfare, time and specialist input before the relevant phase. Site manager reviews the next eight weeks at weekly coordination. |
| Change route | Changed scope, equipment, sequence, people or site conditions reopen the affected plan and task release. |
Delivery stages responsibilities and evidence
| When and owner | Completed arrangement | Evidence required |
|---|---|---|
| Before appointment Authorised specialist / appointed person | A competent lifting planner establishes the load, lifting points, radius, configuration, ground and support conditions, route and landing area for rooftop plant and other lifts. Unknown load weight is resolved before lifting. | Lift plan; ground and load information; equipment and accessory examinations; appointed roles; pre-lift briefing and hand-back |
| Before mobilisation Project manager and competent specialist | The appointed supervisory and slinging/signalling roles are defined for the lift. Equipment and accessories have appropriate inspection and thorough-examination evidence and are suitable for the actual configuration. | Lift plan; ground and load information; equipment and accessory examinations; appointed roles; pre-lift briefing and hand-back |
| At each relevant work stage Site manager and Trade supervisor | The team coordinates overhead and buried services, public and occupied-building boundaries, weather, communications and exclusion. Nobody improvises a lifting point or stands beneath a suspended load. | Lift plan; ground and load information; equipment and accessory examinations; appointed roles; pre-lift briefing and hand-back |
| After change or before handback Site manager and competent reviewer | Changes to crane position, load, ground, path or wind conditions reopen the lifting plan and authorisation. The responsible person checks safe landing and release before removing restraints. | Lift plan; ground and load information; equipment and accessory examinations; appointed roles; pre-lift briefing and hand-back |
Hold points and safe release
Stop a lift when load information, ground capacity, accessory suitability, communication, exclusion or a critical condition differs from the accepted plan.
At a failed prerequisite, the supervisor holds the affected work and protects people. The Site Manager records the boundary and communicates it to adjacent teams. The competent specialist resolves technical conditions; the authorised operating role checks implementation, briefs changes and records the release conditions. Recheck a later change rather than extending an expired acceptance automatically.
Specific plan arrangements
Planning scope
The example covers a scheduled Foundry plant installation. The competent lifting planner obtains verified load mass, lifting points, configuration, radius, path, landing and actual site conditions before selecting equipment.
Engineering prerequisites
Ground support, underground information, outrigger or support arrangement and temporary/permanent structural capacity are resolved by the appropriate competent designers. This example provides no assumed capacity or permissible wind value.
Equipment and people
The lifting supervisor verifies the actual equipment/accessories and competent evidence for the configuration. Define planner, supervisor, operator and slinging/signalling roles and a single communication method.
Field release
Check the installed position, exclusions, public interfaces, load restraint release and current weather against the accepted plan. Unknown or changed inputs hold the lift.
During the lift
Maintain the agreed exclusion and communication; nobody passes beneath the suspended load. Changes in route, ground, load or conditions stop the operation and return to the competent planner.
Landing and handback
Confirm stable support and the accepted securing arrangement before disconnecting lifting equipment. Record actual exceptions, residual restrictions and the final competent handback.
Practical application and review
Worked decision trail
| Fictional situation | Decision and evidence |
|---|---|
| What changes | Foundry receives a plant load whose weight differs from the lift plan. |
| Response | The lifting supervisor holds the lift and returns the load and equipment configuration to the competent planner. |
| Verification | Verify the revised load information, ground basis, accessories and team briefing before lifting. |
How should lifting operations be planned
Plan the load, route, equipment, people and failure response before anyone attaches a hook or starts a truck.
How can the hierarchy of controls prevent dropped loads and unsafe lifting operations
Remove the need for hazardous handling where feasible, then select equipment and controls for the residual lift.
Assurance and update cycle
Supervisors check the controls before relevant work and after change. The Site Manager samples implementation during actual work; the H&S adviser challenges recurring gaps and the plan owner reviews the resulting evidence. Specialist and statutory inspections retain their own competent methods and required intervals. Actions need both completion evidence and a separate effectiveness check; reopen a failed change.