Suspended-person and MEWP rescue plan

BOUK-PLN-WAH-01 · v1.0 · Completed fictional example · DOCX

Define competent rescue actions, equipment, communication and rehearsal.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PLN-WAH-01 | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Define competent rescue actions, equipment, communication and rehearsal.

Example project context

This plan belongs to the fictional 2027 BuildOut portfolio: Eastfield commercial refurbishment, Harbour retail fit out, Foundry light-industrial build and Meadow residential development. Apply the stated arrangements only to the relevant task and phase. The example has no real site address, named staff or technical certification. Project-specific engineering, exposure and rescue information remains a prerequisite to genuine work release.

Plan controlCompleted example arrangement
Accountable roleSite manager coordinates the plan and confirms competent deputies.
Activities and interfacesMEWP emergency lowering and harness-suspension rescue
Risk and policy linkBOUK-POL-WAH and the current task register; map affected work packages before release.
Resources and timingProject manager confirms competent people, equipment, welfare, time and specialist input before the relevant phase. Site manager reviews the next eight weeks at weekly coordination.
Change routeChanged scope, equipment, sequence, people or site conditions reopen the affected plan and task release.

Delivery stages responsibilities and evidence

When and ownerCompleted arrangementEvidence required
Before appointment
Site manager
Plan ceiling service installation and similar tasks to avoid work at height where reasonably practicable. If unavoidable, select suitable collective protection and working equipment before personal fall protection.Access selection and inspection; scaffold or MEWP handover; competence; falling-object and exclusion checks; rescue readiness
Before mobilisation
Project manager and competent specialist
The Site Manager checks podium or MEWP selection against ground, overhead structures, entrapment, reach, load and the actual task. Erected access and scaffold alterations use the appointed competent arrangement.Access selection and inspection; scaffold or MEWP handover; competence; falling-object and exclusion checks; rescue readiness
At each relevant work stage
Site manager and Trade supervisor
Tools, materials, openings and people below are controlled together. The supervisor checks equipment, inspection status, access and changes of work front before use.Access selection and inspection; scaffold or MEWP handover; competence; falling-object and exclusion checks; rescue readiness
After change or before handback
Site manager and competent reviewer
The task has an effective recovery or rescue arrangement where needed, with capable people and equipment available; emergency services are additional support rather than the sole planned provision.Access selection and inspection; scaffold or MEWP handover; competence; falling-object and exclusion checks; rescue readiness

Hold points and safe release

Stop height work when ground, weather, edge protection, access, equipment, falling-object protection or the required rescue capability no longer meets the plan.

At a failed prerequisite, the supervisor holds the affected work and protects people. The Site Manager records the boundary and communicates it to adjacent teams. The competent specialist resolves technical conditions; the authorised operating role checks implementation, briefs changes and records the release conditions. Recheck a later change rather than extending an expired acceptance automatically.

Specific plan arrangements

Example task

The example is ceiling-service installation from a selected MEWP with collective protection. The Site manager seeks a suitable ground-level method first; there is no planned rope-access or unsupported roof task.

Before elevation

The competent supervisor confirms the actual machine, ground, overhead entrapment risks, working envelope and manufacturer emergency-lowering information. Confirm the nominated ground responder can operate the accepted recovery controls.

People and communications

Operator and ground responder practise the approved communication and emergency-lowering arrangement safely under competent instruction. The responder stays available; a missing responder or failed communication holds elevation.

Emergency response

Raise the alarm and stop adjacent hazards where safe. Trained personnel use the machine-specific accepted recovery method only within competence. The emergency coordinator contacts emergency services and directs access as required; nobody climbs or improvises a transfer.

Method failure

If the machine-specific recovery arrangement cannot address the scenario, the task remains held until competent specialist rescue planning supplies suitable people, equipment and a practicable method.

Review

Reassess a changed machine, work position, staffing or rescue obstacle. Keep demonstration and drill evidence separate from this fictional plan; no real rescue rehearsal is asserted.

Practical application and review

Worked decision trail

Fictional situationDecision and evidence
What changesThe selected access platform cannot reach a ceiling task without overreaching.
ResponseThe supervisor stops use and obtains a suitable access method with collective protection and rescue provision where required.
VerificationCheck reach, ground, exclusion and the actual task from a safe position before release.

What must be settled before work starts

Set the exact task and location, choose the safest practicable method, assign competent people, verify access and controls, protect others and make a workable rescue plan.

What needs inspection and records

Check work equipment before use and arrange competent inspections at the frequency and after events required by the relevant law, manufacturer and risk assessment; take defective equipment out of service.

Assurance and update cycle

Supervisors check the controls before relevant work and after change. The Site Manager samples implementation during actual work; the H&S adviser challenges recurring gaps and the plan owner reviews the resulting evidence. Specialist and statutory inspections retain their own competent methods and required intervals. Actions need both completion evidence and a separate effectiveness check; reopen a failed change.

Related SHARE guidance

Guidance Working at Height · Dropped Objects · Scaffolding Safety

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.