Permit issue, suspension, handover and cancellation procedure

BOUK-PRO-PTW · v1.0 · Completed fictional example · DOCX

Identify permit interfaces, competence, isolations, simultaneous operations and restoration.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PRO-PTW | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Identify permit interfaces, competence, isolations, simultaneous operations and restoration.

Scope and operating responsibility

We apply this procedure to Hot work near flammable-product application. Evidence includes Permit register; isolation and testing evidence; interface coordination; suspension and shift handover; reinstatement and closeout. The role controlling the task checks applicability before mobilisation and whenever the scope changes.

RoleRequired action
Site managerOwn this arrangement, confirm competent support and maintain its evidence trail.
Project manager and Site managerCoordinate the actual package, provide resources and verify prerequisites before release; resolve occupied and subcontractor interfaces.
Trade supervisor and workersUse the accepted current method, demonstrate understanding, report changes and stop when critical safeguards are uncertain.
Competent specialist and H&S adviserProvide technical advice within competence; challenge evidence and identify limitations. Management retains the operating decision.

Inputs before using the procedure

Use the current project risk register, relevant survey and design revisions, equipment or product information, worker consultation and the task-specific records listed below. Resolve conflicting or missing information before relying on it. Do not fill missing technical values from an example.

How we carry out the arrangement

1 Plan and obtain reliable information

A permit coordinates high-risk interfaces such as hot work, confined entry, excavation and work on energised or connected systems where required by the assessed arrangement.

2 Verify capability and prerequisites

The issuer and performing team agree the exact boundary, equipment identity, isolations, tests, time limits, affected trades and hand-back. The people verifying the physical controls have the required competence.

3 Control work and interfaces

Isolation includes the actual energy and material sources, stored energy, re-energisation and changes of configuration. A copied permit or tag cannot establish a safe condition.

4 Review change and safe handback

Suspension, shift handover, simultaneous permits and reinstatement use a controlled decision. The accepting operating authority checks the actual condition before return to service.

Stop restrict and restart

Suspend the permit when the scope, operating state, isolation or other prerequisite changes or fails. Restart requires revalidation by the authorised roles.

The person controlling the work makes the affected area safe and notifies the Site Manager. Restart requires the competent technical decision for the actual control, the authorised work-release decision and a fresh briefing of affected people. Record unresolved limits; an updated date or a completed form does not remove a hold.

Practical control detail

A permit should be specific enough that a competent person can verify the job, controls and stop conditions in the field.

Planning should start before the permit is issued and should involve operations, maintenance and competent technical input.

Evidence follow up and learning

Worked decision trail

Fictional situationDecision and evidence
What changesTwo permits require incompatible equipment states.
ResponseThe issuer suspends the affected tasks and reconciles isolations, interfaces and a safe sequence with the operating authority.
VerificationField-verify the revised boundary and obtain fresh acceptance before work resumes.

Supporting arrangement documents

ReferenceHow the document is used
BOUK-REG-PTW-01
Permit register and simultaneous-operations board
Coordinate active permits, isolations, interfaces and shift handovers.
BOUK-PTW-PTW-01
General high-risk work permit
Document work boundary, prerequisites, controls, time validity and accountable release.
BOUK-FRM-PTW-01
Isolation certificate and lock register
Record energy source, isolation point, lock owner, verification and restoration.
BOUK-FRM-PTW-02
Permit suspension, handover and cancellation record
Control temporary stop, personnel/shift change and final safe handback.
BOUK-CHK-PTW-01
Permit-system audit and field verification
Test whether permits match actual site conditions and controls.

Retain the record ID, task, location, competent author, revision, date, decision, restrictions, action owner and separate effectiveness evidence. Restrict personal and health information and apply the relevant retention rule. File genuine results separately from teaching examples.

Guidance Permit-to-work Systems · Isolation, Lockout and Line Breaking

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.