Free training · Approx. 2h–3h · estimated self-paced learning, including activities and assessment.
Public teaching is free without an account. A free learner account is required for confirmed LMS assessment, completion and certificate records. See the full course outline and access routes.
Teaching and applied cases for accessible study. The interactive course records assessed completion.
Lesson 1
Define the dig before choosing controls
A route change can alter ground loads, services, temporary works and people exposed. Reconcile the plan with the actual location.
What is excavation safety in practical terms?
An open excavation is a changing work area whose sides, base and nearby loads must remain stable throughout entry, digging, inspection and reinstatement.
The approved pre-dig method is the starting condition. The field team compares it with the soil exposed, water inflow, structures and service positions actually found; a mismatch is a hold point, not permission to improvise.
The companion Excavation page covers route selection, information and release before the first cut. This page follows the competent check after the ground is open.
Excavation safety elements - Excavation safety elements
Element
Why it matters
Evidence
Pre-construction information
Ground, services and structural information influence method and risk.
Drawings, surveys and site information pack.
Risk assessment and method
Controls must match depth, ground and work activity.
RAMS, excavation plan and permit to dig.
Temporary works
Support, shoring or battering may need design and approval.
Design brief, drawings and inspection records.
Service avoidance
Cable, gas, water and telecom strikes can kill and disrupt.
HSG47-style plan, scan, mark and trial-hole records.
Inspection
Conditions change with weather, water, loading and vibration.
Competent inspection reports and defect actions.
Emergency planning
Collapse, engulfment or service strike needs rapid controlled response.
Rescue plan, briefings and emergency contacts.
Visual practice · Define the dig before choosing controls
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.What is excavation safety in practical terms?
An open excavation is a changing work area whose sides, base and nearby loads must remain stable throughout entry, digging, inspection and reinstatement. The approved pre-dig method is the starting condition. The field team compares it with the soil exposed, water inflow, structures and service positions actually found; a mismatch is a hold point, not permission to improvise. The companion Excavation page covers route selection, information and release before the first cut.
How should excavation work be planned before digging starts?
The workface plan must show today’s sequence: where support is installed or removed, who may enter, where spoil and plant stand, how services are exposed, and what happens if water or ground changes. At shift handover, compare the authorised method with the excavation as left, inspection findings and the next operation. A new depth, crossing, vehicle load or nearby dig calls for review before the crew changes the face.
How harm develops in the linked model
Plans, colours and nominal depths cannot prove actual location or identity. A strike may cause arc burns, gas release, flooding or loss of essential services.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How should excavation work be planned before digging starts?
The workface plan must show today’s sequence: where support is installed or removed, who may enter, where spoil and plant stand, how services are exposed, and what happens if water or ground changes.
At shift handover, compare the authorised method with the excavation as left, inspection findings and the next operation. A new depth, crossing, vehicle load or nearby dig calls for review before the crew changes the face.
Pre-dig planning checks - Pre-dig planning checks
Check
What to confirm
Record
Need to excavate
Can the work be avoided, rerouted or completed by trenchless method?
Design review and method selection.
Services
Which utilities, drainage, ducts or unknown services may be present?
Service drawings, surveys and HSG47 plan.
Ground
Soil type, made ground, water, contamination and previous disturbance.
Ground information and site observations.
Structures
Nearby walls, roads, scaffolds, foundations and trees.
Structural review and exclusion distances.
Support
Shoring, trench box, battering, benching or no-entry method.
Temporary works design and approval.
People and plant
Access, segregation, edge loads and public interface.
Traffic plan and induction briefing.
Emergency
Collapse, service strike, flooding or atmosphere response.
Rescue plan and emergency contacts.
Apply the learning
The drainage route moves closer to an occupied building after the method was agreed.
Decision and explanation
Review the changed route, nearby foundations and sequence with the competent planning team before release.
A route change can alter ground loads, services, temporary works and people exposed. Reconcile the plan with the actual location.
Lesson 2
Who plans, checks and releases?
Design information and a competent workface check perform different jobs; both must connect through the work sequence.
Who needs the live excavation check?
The workface supervisor, competent inspector, temporary-works lead, groundworkers and plant operators must share one current picture of the open excavation.
The planner hands over the authorised method; the field team verifies the support, exposed services, access, water, edge loads and exclusion zone at the actual location. An operator should know who can stop entry when those conditions change.
Visual practice · Who plans, checks and releases?
Actual SHAREsimulate model capture · The excavation inspection no longer matches today’s trench. The exercise description supplies the scenario; a still image cannot establish hidden conditions.Investigate 1: Stair access
The stair and its handrails are visible. Their presence does not establish that access can reopen after the stated overnight changes. Ask what the current inspection covers and how access is controlled until release.
Investigate 2: Crossing beside the excavation
A scaffold crossing and edge protection are shown. Compare the current arrangement with the changed support and loading information in the fictional case; do not accept yesterday’s inspection as proof of today’s condition.
Investigate 3: Perimeter barrier
The barrier marks a boundary beside the excavation. Investigate the changed vehicle route and whether the inspection and loading controls address the current layout. A still image cannot establish stability.
Who needs the live excavation check?
The workface supervisor, competent inspector, temporary-works lead, groundworkers and plant operators must share one current picture of the open excavation. The planner hands over the authorised method; the field team verifies the support, exposed services, access, water, edge loads and exclusion zone at the actual location. An operator should know who can stop entry when those conditions change.
What assurance record matters at the open excavation?
A management system should connect the design and permit to daily observation, defect escalation, corrective action and documented release. Official management guidance: HSE Managing for health and safety (HSG65) Audit whether inspection records correspond to the actual face, support and weather; whether changed ground prompted review; and whether workers could stop the job. A procedure or ISO certificate alone does not prove that the trench is safe to enter.
How harm develops in the linked model
Rain, ground loading and changes to support can affect the trench and scaffold bearings together. An earlier signed report or a closed gate is not proof that today’s route and workface are safe.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How can this guidance help in practice?
Workers and people carrying out the task
Use the Excavations: ground, services and inspection guidance to recognise relevant hazards, understand the precautions and identify when to stop, report a problem or ask for competent support.
Supervisors and managers
Use the task examples and control checks to plan work, brief the team, check implementation and assign improvements with owners and follow-up.
Safety, health, risk and assurance professionals
Use the explanations, sources and operational examples to develop assessments, audits and control verification. Check the actual scope and jurisdiction before applying a duty.
Learners, trainers and organisational decision makers
Use the definitions and examples to connect theory with workplace decisions, build briefings and ask informed questions. This page does not certify competence or authorise work.
What assurance record matters at the open excavation?
A management system should connect the design and permit to daily observation, defect escalation, corrective action and documented release.
Audit whether inspection records correspond to the actual face, support and weather; whether changed ground prompted review; and whether workers could stop the job. A procedure or ISO certificate alone does not prove that the trench is safe to enter.
Apply the learning
The designer has sent a support drawing, but nobody is assigned to inspect the installed system.
Decision and explanation
Confirm competent inspection, supervision, design interfaces and authority to hold entry.
Design information and a competent workface check perform different jobs; both must connect through the work sequence.
Lesson 3
Read the ground and its neighbours
Ground, water and adjoining foundations are interacting conditions. A visual guess at a universal slope cannot establish stability.
What should the workface scan cover?
Scan the face, base, edges, access and nearby activities together: collapse, falling people or material, buried services, vehicles, water and hazardous atmospheres can interact.
A displaced support strut, fresh fissure, saturated layer, unstable spoil, unguarded edge or restricted escape route is a live stop-work signal. The inspector records the change, keeps people clear and gets the support or sequence reassessed before re-entry.
Visual practice · Read the ground and its neighbours
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.What should the workface scan cover?
Scan the face, base, edges, access and nearby activities together: collapse, falling people or material, buried services, vehicles, water and hazardous atmospheres can interact. A displaced support strut, fresh fissure, saturated layer, unstable spoil, unguarded edge or restricted escape route is a live stop-work signal. The inspector records the change, keeps people clear and gets the support or sequence reassessed before re-entry.
What must the field team check when conditions change?
A competent inspection tests whether the as-built trench still matches the approved support and access arrangement. If a change undermines that basis, stop entry, protect people at the edge and obtain a revised competent decision before restarting.
How harm develops in the linked model
A slope that stood yesterday may fail when water, ground conditions or nearby loading change; adjacent foundations may also be undermined.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What must the field team check when conditions change?
A competent inspection tests whether the as-built trench still matches the approved support and access arrangement. If a change undermines that basis, stop entry, protect people at the edge and obtain a revised competent decision before restarting.
Observation
Immediate field action
Restart evidence
Crack, bulge or soil fall
Stop entry and keep people and plant clear of the edge.
Competent reassessment and revised support or slope.
Water, rain or seepage
Stop entry and review stability, inundation and pumping effects.
Dewatering and support method confirmed for actual conditions.
New edge load or vibration
Move surcharge and plant back; protect the exclusion zone.
Support design checked against changed load.
Support movement or missing component
Stop entry; never improvise removal of a strut or trench box.
Designed repair, installation and competent inspection.
Unexpected service or atmosphere
Stop digging or entry, isolate people and seek specialist control.
Verified service route or atmosphere/rescue plan as applicable.
Apply the learning
A previously dry face is cracked beside a wall after overnight rain.
Decision and explanation
Keep people out and obtain a competent review of the ground, wall and protective system.
Ground, water and adjoining foundations are interacting conditions. A visual guess at a universal slope cannot establish stability.
Lesson 4
Plan, locate and expose services
Planning, locating and safe excavation are complementary controls; uncertainty must be resolved before the tool reaches the service.
What safe system does HSG47 expect for underground services?
The safe system should begin before anyone arrives with plant or a breaker. Clients and designers should obtain available information, identify constraints and provide it early. Contractors should review the information, assess the work method, arrange competent survey and decide how the ground will be opened safely.
Locating and identifying services is then used to reduce uncertainty at the workface. Plans are interpreted alongside locating-device results, site features, visible covers, cabinets, poles, meters, gullies, valves, scars in reinstatement and local knowledge. The service route is marked clearly and the permit or briefing explains what those marks mean.
Safe excavation is the final control, not the first. If the work starts with an excavator because the programme is tight, the system has already weakened. Ground should be opened cautiously, trial holes used where needed, exposed services supported and protected, and work stopped when conditions do not match the plan.
Plan the work. Obtain records, identify service owners, choose method and build risk controls into the programme. Utility searches, drawings, RAMS and construction phase plan.
Locate and identify. Use competent survey, CAT/Genny, GPR where suitable, visible features and trial holes. Survey report, scan records, equipment checks and marked drawings.
Mark and communicate. Mark routes clearly and brief the team on meaning, uncertainty and limits. Marked work area, toolbox talk and permit conditions.
Excavate safely. Use controlled hand digging, vacuum excavation or restricted plant methods near services. Permit to dig, supervisor checks and inspection records.
Update and learn. Record actual positions, strikes, near misses and unexpected findings. As-built updates, investigation reports and action close-out.
Visual practice · Plan, locate and expose services
Actual SHAREsimulate model capture · A service plan is mistaken for proof of clearance. The exercise description supplies the scenario; a still image cannot establish hidden conditions.What safe system does HSG47 expect for underground services?
HSG47 is built around planning the work, locating and identifying buried services, and safe excavation. See HSE HSG47 avoiding danger from underground services The safe system should begin before anyone arrives with plant or a breaker. Clients and designers should obtain available information, identify constraints and provide it early. Contractors should review the information, assess the work method, arrange competent survey and decide how the ground will be opened safely.
How should work be planned before excavation starts?
Planning should identify what might be underground, who owns it, how reliable the information is and how the work will avoid damage. See HSE HSG47 avoiding danger from underground services Planning must start with the task: excavation, post installation, trenching, piling, moling, drilling, site investigation, demolition, resurfacing, landscaping or breaking concrete. Each method has a different strike mechanism. A post rammer can pierce a cable, a breaker can damage a shallow service, a piling rig can hit deep assets, and trenchless work can intersect services away from the launch pit.
How harm develops in the linked model
Plans, colours and nominal depths cannot prove actual location or identity. A strike may cause arc burns, gas release, flooding or loss of essential services.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How should work be planned before excavation starts?
Planning must start with the task: excavation, post installation, trenching, piling, moling, drilling, site investigation, demolition, resurfacing, landscaping or breaking concrete. Each method has a different strike mechanism. A post rammer can pierce a cable, a breaker can damage a shallow service, a piling rig can hit deep assets, and trenchless work can intersect services away from the launch pit.
The client should provide pre-construction information where CDM applies. That includes known underground services, site surveys, as-built records, previous investigations, private services and constraints. The contractor should not accept vague statements such as 'services to be confirmed on site' without a clear plan for confirmation.
Planning should also include service isolation where possible, emergency contacts, exclusion zones, traffic and pedestrian management, ground conditions, excavation support, confined-space risk, contaminated land, water ingress, night work, public interface and how changes will be authorised.
Utility searches. Identifies known service owners and indicative routes. Responses, plans and correspondence.
Private services. Private estates often contain unrecorded lighting, drainage, power or process lines. Estate drawings, interviews and site survey.
Work method. Different tools create different strike risks. Method statement and plant/tool selection.
Isolation feasibility. Dead or isolated services reduce consequence. Isolation certificate or utility confirmation.
Emergency plan. People need immediate actions before a strike occurs. Emergency contacts, briefing and site plan.
Competence. Poor interpretation of scans or drawings can be as dangerous as no survey. Training, assessment and supervision record.
Apply the learning
The utility drawing and site markings disagree at a proposed connection.
Decision and explanation
Hold excavation at the conflict and reconcile current information, location and safe exposure.
Planning, locating and safe excavation are complementary controls; uncertainty must be resolved before the tool reaches the service.
Lesson 5
What a locator can and cannot tell you
No signal does not establish absence. Service material, depth, conditions, equipment and operator competence affect detection.
How should buried services be located and identified?
Buried services should be located by combining records, visual clues, locating devices, competent interpretation and trial holes. See HSE underground cables
Cable avoidance tools are useful but not magic. They can detect many conductive services, especially when used with a signal generator, but they can miss non-conductive pipes, plastic services, poorly earthed cables, congested areas or services masked by other signals. Ground penetrating radar can help in some conditions, but its performance depends on ground type, depth, object size, moisture and operator competence.
The scan should not be a single sweep done at the start of the week. Locating devices should be used frequently and repeatedly as work progresses because the excavation face changes, services may be exposed, and the route may not match the first interpretation.
Trial holes are often the point where uncertainty becomes knowledge. They should be positioned and excavated carefully to confirm route and depth before mechanical excavation continues. Where a service is exposed, it should be identified, supported, protected and not used as a step, handle, prop or working platform.
Utility drawings. Identifying likely service owners, routes and constraints. May be incomplete, approximate, out of date or missing private services.
CAT passive modes. Detecting some live power and radio signals. Can miss quiet, dead, shielded or non-conductive services.
CAT with Genny. Applying a signal to improve tracing of conductive services. Requires correct connection/induction and competent interpretation.
Ground penetrating radar. Detecting some non-metallic or unknown buried features. Affected by ground conditions, depth, clutter and operator skill.
Trial holes. Confirming actual position and depth. Must be dug safely and may still require service-owner advice.
Site clues. Covers, valves, poles, meters, trenches, scars and local knowledge. Clues support the assessment but do not prove absence.
A utility survey can improve the plan, but cannot prove that every buried service has been found. HSG47 requires planning, locating and identifying services, followed by safe excavation. HSE HSG47 underground-services guidance
Vacuum excavation and jetting can assist safe exposure, but method selection must account for ground conditions, ejected material and damage to older or fragile services. Confirm the utility owner’s requirements, use competent operators and repeat locating as the excavation changes; neither suction nor a survey label makes an unknown service safe.
Visual practice · What a locator can and cannot tell you
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.How should buried services be located and identified?
Buried services should be located by combining records, visual clues, locating devices, competent interpretation and trial holes. See HSE underground cables Cable avoidance tools are useful but not magic. They can detect many conductive services, especially when used with a signal generator, but they can miss non-conductive pipes, plastic services, poorly earthed cables, congested areas or services masked by other signals. Ground penetrating radar can help in some conditions, but its performance depends on ground type, depth, object size, moisture and operator competence.
How should buried services be marked and communicated?
Service markings should be clear, current, protected from confusion and explained to everyone working in the area. See HSE HSG47 avoiding danger from underground services Markings are a communication control. They help plant operators, groundworkers, supervisors and visitors understand where extra caution is needed. They should match the latest scan and permit, be refreshed if weather or traffic removes them, and be protected where the work area changes.
How harm develops in the linked model
Plans, colours and nominal depths cannot prove actual location or identity. A strike may cause arc burns, gas release, flooding or loss of essential services.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How should buried services be marked and communicated?
Markings are a communication control. They help plant operators, groundworkers, supervisors and visitors understand where extra caution is needed. They should match the latest scan and permit, be refreshed if weather or traffic removes them, and be protected where the work area changes.
Colour conventions and plans can support recognition, but they should not be treated as proof. Some services are not laid to expected depth, some are abandoned but still hazardous, some private services are unrecorded, and some routes move around obstacles. The safer phrase is: 'This is the best verified information we currently have, and these are the limits of confidence.'
The briefing should explain the markings, no-dig zones, hand-dig zones, trial-hole locations, plant exclusion rules, emergency stop points and who can authorise a change.
Ground markings. Mark confirmed and suspected routes, trial holes and exclusion areas. Makes risk visible at the workface.
Permit drawing. Attach marked-up plan to the permit or task briefing. Connects authorisation to actual location.
Briefing. Explain markings, uncertainty, limits and stop-work triggers. Prevents workers guessing what a colour or line means.
Refresh checks. Check markings after rain, traffic, resurfacing or shift change. Prevents people working from lost or stale information.
As-built update. Record actual locations and unexpected findings. Improves future planning and estate records.
What must a replacement crew understand before digging?
A paint mark is a communication aid; its meaning depends on the survey, limitations and confirmed findings behind it. When markings are covered, washed away or displaced by work, do not reconstruct them from memory and continue. Re-establish the service information with competent locating and verification appropriate to the planned method. A replacement crew must understand both what is known and what remains uncertain.
For an illustrative trench reopened by a later shift, the supervisor walks the work area with the crew, compares current plans and survey findings with the surviving marks and identifies verified trial holes, exposed services and protected areas. Confirm the exact extent of the authorised task, tools, plant restrictions, owner contacts and stop conditions. If the proposed depth, route or work method has changed, or the marks cannot be related reliably to the evidence, hold the affected excavation and update the assessment and permit before briefing the crew. Yesterday’s completed survey does not automatically authorise today’s different excavation.
Guidance and scope: Original SHARE crew-change example applying HSE GB underground-service guidance. Plans and scans have limitations; no universal safe digging depth, offset or permission to assume an unmarked area is clear is given. HSE HSG47 avoiding danger from underground servicesHSE underground cables
Apply the learning
A locator gives no signal over an area shown as containing a non-metallic service.
Decision and explanation
Treat the service as unresolved and use competent locating and safe exposure arrangements.
No signal does not establish absence. Service material, depth, conditions, equipment and operator competence affect detection.
Lesson 6
Permits and safe exposure
A permit coordinates verified controls. It cannot replace the physical checks and safe excavation method it requires.
A permit to dig is not a permission slip for excavation. It is a control point where the supervisor checks that the work area, service information, survey, equipment, people, method, emergency arrangements and limits are ready. If the permit is issued from an office without field verification, it is weak.
The permit should be specific to the location and task. It should identify the permitted area, depth, method, drawings used, services expected, survey equipment used, serial/calibration status, marks on the ground, isolation status, plant restrictions, hand-dig requirements, supervision, emergency contacts, hold points and expiry time.
The hand-back is just as important. The supervisor should confirm whether services were exposed, supported, damaged, diverted, made dead, re-energised, backfilled, protected or left with temporary arrangements.
Scope. Exact work area, depth, method and timing. Permit description and marked drawing.
Information. Utility plans, private-service records and survey results reviewed. Attached plans and survey report.
Detection. Competent scan completed with suitable equipment. CAT/Genny serial, check date and operator name.
Controls. Hand digging, plant exclusion, isolation, barriers and emergency arrangements defined. Permit conditions and briefing signatures.
Authorisation. Supervisor verifies workface conditions before work starts. Field sign-off and hold points.
Cancellation. Area left safe, services protected and records updated. Close-out sign-off and as-built notes.
Visual practice · Permits and safe exposure
Actual SHAREsimulate model capture · A service plan is mistaken for proof of clearance. The exercise description supplies the scenario; a still image cannot establish hidden conditions.What should a permit to dig control?
A permit to dig should confirm that the ground-breaking work has been planned, checked, briefed, authorised and handed back safely. See HSE HSG47 avoiding danger from underground services A permit to dig is not a permission slip for excavation. It is a control point where the supervisor checks that the work area, service information, survey, equipment, people, method, emergency arrangements and limits are ready. If the permit is issued from an office without field verification, it is weak.
How should excavation be carried out safely near buried services?
Excavation near buried services should be cautious, supervised and adjusted as information improves. See HSE underground cables Safe digging is a set of behaviours. Workers should not use picks, breakers, pins, forks or excavator teeth aggressively into ground where services may exist. Once a service is suspected or located, excavation should normally proceed alongside it rather than directly above it, using suitable hand tools or vacuum excavation where appropriate.
How harm develops in the linked model
Plans, colours and nominal depths cannot prove actual location or identity. A strike may cause arc burns, gas release, flooding or loss of essential services.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How should excavation be carried out safely near buried services?
Excavation near buried services should be cautious, supervised and adjusted as information improves. See HSE underground cables
Safe digging is a set of behaviours. Workers should not use picks, breakers, pins, forks or excavator teeth aggressively into ground where services may exist. Once a service is suspected or located, excavation should normally proceed alongside it rather than directly above it, using suitable hand tools or vacuum excavation where appropriate.
Mechanical excavation can rapidly turn uncertainty into a strike. If plant is used, it should operate under defined limits, with a banksman or supervisor, clear exclusion zones, no blind digging, no scraping directly across services and stop points before entering higher-risk zones.
Exposed services must be protected. Cables and pipes can be damaged by being left unsupported, struck by spoil, used as steps, exposed to weather, bent, scraped, vibrated or backfilled with unsuitable material. Backfilling should avoid sharp materials and should restore protection, support and marker information.
Hand digging. Use controlled, suitable tools near known or suspected services. Aggressive use of picks, bars or breakers.
Trial holes. Confirm route and depth before wider excavation. Assuming drawings prove exact location.
Plant control. Set exclusion zones, depth limits and supervision. Excavator used before service position is confirmed.
Service support. Support and protect exposed services. Cables left hanging across trench or used as access.
Backfill. Use suitable material and reinstate markers/protection. Sharp rubble or concrete placed against service.
Stop-work trigger. Pause if conditions differ from plan. Continuing after unexpected pipe, duct or cable is found.
Apply the learning
A permit is signed, but the planned trial holes have not been completed.
Decision and explanation
Hold the intrusive stage until the safe exposure method and actual conditions are verified.
A permit coordinates verified controls. It cannot replace the physical checks and safe excavation method it requires.
Lesson 7
Support, shielding and safe slopes
A shield protects people within its design limits; it is not automatically a shoring design for ground or structures outside it.
How should collapse risk be controlled?
A face can move between inspections. Watch for cracks, bulging, sloughing, loss of support contact and settlement beside the trench; keep people out while a competent person decides what changed.
Use the support or site-specific batter selected for the actual soil, depth, water and surcharge. Confirm that a trench box is installed within its design limits and that no worker must stand in an unsupported section while moving it.
A box mainly shields workers; shoring supports the ground. Either can be defeated by poor installation, edge loads or changed conditions. PPE and a signed permit do not prevent burial.
Collapse control options - Collapse control options
Control
When it may be used
Key checks
Avoid entry
Inspection, connection or installation can be done from outside.
Tooling, visibility and rescue implications.
Trench box
Linear trenches where box movement is practical.
Correct size, installation, ground contact and access.
Shoring
Where sides need direct support.
Competent design, installation and inspection.
Battering
Where space allows sides to be sloped back.
Safe angle, soil type and weather effects.
Benching
Where stepped excavation controls face height.
Geotechnical suitability and edge stability.
Temporary works design
Complex depth, poor ground, adjacent structures or unusual loading.
Design brief, approval and inspection regime.
Visual practice · Support, shielding and safe slopes
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.How should collapse risk be controlled?
A face can move between inspections. Watch for cracks, bulging, sloughing, loss of support contact and settlement beside the trench; keep people out while a competent person decides what changed. Use the support or site-specific batter selected for the actual soil, depth, water and surcharge. Confirm that a trench box is installed within its design limits and that no worker must stand in an unsupported section while moving it.
What must the field team check when conditions change?
A competent inspection tests whether the as-built trench still matches the approved support and access arrangement. If a change undermines that basis, stop entry, protect people at the edge and obtain a revised competent decision before restarting.
How harm develops in the linked model
Ground can collapse suddenly and bury or crush a person. A trench box protects only when correctly selected, installed and used within its designed arrangement.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What must the field team check when conditions change?
A competent inspection tests whether the as-built trench still matches the approved support and access arrangement. If a change undermines that basis, stop entry, protect people at the edge and obtain a revised competent decision before restarting.
Observation
Immediate field action
Restart evidence
Crack, bulge or soil fall
Stop entry and keep people and plant clear of the edge.
Competent reassessment and revised support or slope.
Water, rain or seepage
Stop entry and review stability, inundation and pumping effects.
Dewatering and support method confirmed for actual conditions.
New edge load or vibration
Move surcharge and plant back; protect the exclusion zone.
Support design checked against changed load.
Support movement or missing component
Stop entry; never improvise removal of a strut or trench box.
Designed repair, installation and competent inspection.
Unexpected service or atmosphere
Stop digging or entry, isolate people and seek specialist control.
Verified service route or atmosphere/rescue plan as applicable.
Apply the learning
The crew calls a trench box a guarantee that the surrounding ground and nearby wall cannot move.
Decision and explanation
Check the design purpose, installation sequence and protection of adjoining structures before entry.
A shield protects people within its design limits; it is not automatically a shoring design for ground or structures outside it.
Lesson 8
Edge loads and falling material
Surcharge can contribute to failure before visible warning. Setbacks depend on the site-specific protective arrangement.
How should the live edge be controlled?
Keep people, spoil, equipment and moving plant away from the edge; provide barriers or covers suited to the people and vehicles present.
Inspect the edge after loading, weather or traffic changes. A barrier does not make an overloaded edge stable. If set-back space is unavailable, a competent designer must address surcharge and support before the job resumes. Provide a protected crossing where people must pass over the opening.
Visual practice · Edge loads and falling material
Actual SHAREsimulate model capture · A proposed spoil change would load the excavation edge. The exercise description supplies the scenario; a still image cannot establish hidden conditions.How should the live edge be controlled?
Keep people, spoil, equipment and moving plant away from the edge; provide barriers or covers suited to the people and vehicles present. Inspect the edge after loading, weather or traffic changes. A barrier does not make an overloaded edge stable. If set-back space is unavailable, a competent designer must address surcharge and support before the job resumes.
How should plant and vehicle interface be controlled?
Set plant movements around the opening the crew actually has today. Barriers, banksman arrangements and spoil locations must prevent people being struck and the edge being surcharged. A delivery, lift or compactor can add a load absent from the original support calculation. Stop its approach until the competent lead confirms the permitted distance and sequence.
How harm develops in the linked model
Surcharge and vibration can destabilise the face, while falling spoil or a vehicle can strike people below.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How should plant and vehicle interface be controlled?
Set plant movements around the opening the crew actually has today. Barriers, banksman arrangements and spoil locations must prevent people being struck and the edge being surcharged.
A delivery, lift or compactor can add a load absent from the original support calculation. Stop its approach until the competent lead confirms the permitted distance and sequence.
The operator should know the service exclusion zone, crossing point and signal to stop. Do not swing a bucket over entrants or let access routes be blocked by vehicles.
One-way routes, reversing controls and visibility.
Service exposure
Bucket damages cables or pipes.
Hand dig or controlled methods near services.
Emergency access
Plant blocks rescue or emergency routes.
Access route kept clear.
Apply the learning
Spoil and a delivery vehicle are moved toward an excavation to clear a traffic route.
Decision and explanation
Stop the changed loading and reinstate the designed setbacks and edge protection after review.
Surcharge can contribute to failure before visible warning. Setbacks depend on the site-specific protective arrangement.
Lesson 9
Safe access and protected edges
Access must be usable without defeating the protective system or creating a second exposure.
What must be confirmed before anyone enters an excavation?
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release. Keep people out when any of those controls is uncertain.
Best-practice guide · six simple steps
Visual practice · Safe access and protected edges
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.What must be confirmed before anyone enters an excavation?
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release. Keep people out when any of those controls is uncertain. CAT and Genny are service-locating aids, not proof that the trench is clear. Keep the plans, locator record and safe-exposure method at the workface; the supervisor must reconcile any new indication before digging continues.
Which observations require immediate reassessment?
Stop entry for cracked or bulging faces, displaced shoring, water seepage or pooling, unexpected services, falling material, new plant loads, failed edge protection or an unsafe access route. Keep people and plant clear while a competent person checks the support, ground, services and rescue position. A previously signed permit or morning inspection cannot authorise continued work after a material change.
How harm develops in the linked model
A failed bearing, missing guardrail, slippery tread or obstructed exit can cause a fall or prevent escape. A gate or inspection tag alone does not establish stability or safe access.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
Best-practice guide: Excavations: ground, services and inspection
Start with the key actions, then explore value, a workplace example, harm, stronger controls and further help. Choose a step or use Previous and Next; the guide does not advance automatically.
Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links.
Read all six steps as text
1. What must be confirmed before anyone enters an excavation?
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release.
Control the task: Locate, mark, expose and protect services before digging.
Verify before release: Excavation decision record.
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release. Keep people out when any of those controls is uncertain. An open excavation can fail without warning when soil, water, support, edge loads or vibration change.
Apply it: Which part of this plan would you check at the workface before authorising the task?
An open excavation can fail without warning when soil, water, support, edge loads or vibration change. Before entry and after each relevant change, a competent person must verify the actual support or site-specific batter, safe access, buried services, plant separation and rescue arrangements. Inspection observations, photographs, temporary-works decision, revised method, briefing and hand-back log.
Apply it: What evidence would show that the change improves this task, rather than only completing a record?
Fictional example: a practical application of the existing topic lesson.
Setting: Drainage trench in layered wet ground beside an occupied building and delivery route.
Act: Inspect the open face and installed box; move vehicle and crew away from the edge.
Hold / review: Do not enter or pump by assumption while the changed ground and safe correction method are unresolved.
Stop entry on the crack and water; reassess support, drainage, foundation and service exposure. Verify corrected support, access and water control; brief the crew and record a fresh release.
Apply it: At which point would you hold this example, and what evidence would allow it to proceed?
Connect the task, the route to the person and the control that can fail.
Source / exposure: Scan the face, base, edges, access and nearby activities together: collapse, falling people or material, buried services, vehicles, water and hazardous atmospheres can interact.
Possible consequence: A displaced support strut, fresh fissure, saturated layer, unstable spoil, unguarded edge or restricted escape route is a live stop-work signal.
Control failure: The inspector records the change, keeps people clear and gets the support or sequence reassessed before re-entry.
Scan the face, base, edges, access and nearby activities together: collapse, falling people or material, buried services, vehicles, water and hazardous atmospheres can interact.
Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby?
Collapse and engulfment: Control ground movement, edge loading, support, battering or shoring.
Buried services: Locate, mark, expose and protect services before digging.
Water ingress: Assess groundwater, rain, flooding, pumps and emergency escape.
Plant interface: Separate excavations from plant, spoil, lifting and vehicle movement.
Decision tree: Decide whether excavation needs design, temporary works, permit-to-dig or specialist support. Collapse and engulfment: Control ground movement, edge loading, support, battering or shoring. Buried services: Locate, mark, expose and protect services before digging. Water ingress: Assess groundwater, rain, flooding, pumps and emergency escape. Plant interface: Separate excavations from plant, spoil, lifting and vehicle movement. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged.
Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk?
Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status.
Apply it: Which official source and full-topic section will you use to resolve the next decision?
Simplified learning guide. Use the full topic, current official guidance and the actual work arrangements. Workplace scenarios labelled fictional are illustrative examples.
CAT and Genny are service-locating aids, not proof that the trench is clear. Keep the plans, locator record and safe-exposure method at the workface; the supervisor must reconcile any new indication before digging continues.
At a wet pit beside a wall, close access while a competent lead checks whether the wall foundation and temporary support still satisfy the design. Re-open only after the revised sequence, water control and traffic set-back are briefed and verified.
Control ground movement, edge loading, support, battering or shoring.
Design or inspection record.
Buried services
Locate, mark, expose and protect services before digging.
Plans, CAT/Genny checks and trial holes.
Water ingress
Assess groundwater, rain, flooding, pumps and emergency escape.
Inspection and weather review.
Plant interface
Separate excavations from plant, spoil, lifting and vehicle movement.
Traffic and exclusion plan.
Stop-work triggers
Cracks, water, unsupported sides, unmarked services or changed ground stop the job.
Stop-work and review log.
Rescue warning
Do not improvise trench rescue; call emergency services and protect others from entering.
Emergency briefing.
Which observations require immediate reassessment?
Stop entry for cracked or bulging faces, displaced shoring, water seepage or pooling, unexpected services, falling material, new plant loads, failed edge protection or an unsafe access route.
Keep people and plant clear while a competent person checks the support, ground, services and rescue position. A previously signed permit or morning inspection cannot authorise continued work after a material change.
Apply the learning
Workers must climb over a trench-box strut to reach a short unsecured ladder.
Decision and explanation
Keep entry closed until a safe access route and edge protection are provided.
Access must be usable without defeating the protective system or creating a second exposure.
Lesson 10
Water, pumping and stability
Dewatering can affect ground and structures. It belongs in the protective design and inspection process.
How do water, weather and ground conditions change excavation risk?
A new seep, rain pulse or pump change can alter face stability and escape. Close entry where the agreed support or batter can no longer be relied upon.
Check the source and path of water, erosion at the toe, saturated spoil, nearby foundations and whether pumping could draw material from under support. A competent lead must decide the correction and inspection needed before re-entry.
The decision should record the observed condition and action, rather than merely noting “weather checked”. Keep plant and people clear of a softened edge.
Water and ground risk controls - Water and ground risk controls
Condition
Risk
Control
Rainfall
Softens or erodes sides and increases collapse risk.
Weather trigger inspection and support review.
Groundwater
Causes inflow and loading on support.
Dewatering design and monitored pumping.
Surface water
Runs into excavation and undermines edges.
Drainage, bunding and diversion.
Made ground
Unpredictable strength and contamination.
Ground investigation and conservative support.
Vibration
Destabilises sides and adjacent structures.
Plant exclusion and monitoring.
Adjacent structures
Excavation may undermine walls, roads or scaffolds.
Structural assessment and temporary works.
Visual practice · Water, pumping and stability
Actual SHAREsimulate model capture · Water and a pump create new excavation risks. The exercise description supplies the scenario; a still image cannot establish hidden conditions.How do water, weather and ground conditions change excavation risk?
A new seep, rain pulse or pump change can alter face stability and escape. Close entry where the agreed support or batter can no longer be relied upon. Check the source and path of water, erosion at the toe, saturated spoil, nearby foundations and whether pumping could draw material from under support. A competent lead must decide the correction and inspection needed before re-entry.
How should excavation work be planned before digging starts?
The workface plan must show today’s sequence: where support is installed or removed, who may enter, where spoil and plant stand, how services are exposed, and what happens if water or ground changes. At shift handover, compare the authorised method with the excavation as left, inspection findings and the next operation. A new depth, crossing, vehicle load or nearby dig calls for review before the crew changes the face.
How harm develops in the linked model
Water can erode support and flood the work area. Exhaust, contamination or oxygen depletion can create dangerous atmospheres; an excavation may also meet the confined-space definition.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How should excavation work be planned before digging starts?
The workface plan must show today’s sequence: where support is installed or removed, who may enter, where spoil and plant stand, how services are exposed, and what happens if water or ground changes.
At shift handover, compare the authorised method with the excavation as left, inspection findings and the next operation. A new depth, crossing, vehicle load or nearby dig calls for review before the crew changes the face.
Pre-dig planning checks - Pre-dig planning checks
Check
What to confirm
Record
Need to excavate
Can the work be avoided, rerouted or completed by trenchless method?
Design review and method selection.
Services
Which utilities, drainage, ducts or unknown services may be present?
Service drawings, surveys and HSG47 plan.
Ground
Soil type, made ground, water, contamination and previous disturbance.
Ground information and site observations.
Structures
Nearby walls, roads, scaffolds, foundations and trees.
Structural review and exclusion distances.
Support
Shoring, trench box, battering, benching or no-entry method.
Temporary works design and approval.
People and plant
Access, segregation, edge loads and public interface.
Traffic plan and induction briefing.
Emergency
Collapse, service strike, flooding or atmosphere response.
Rescue plan and emergency contacts.
Apply the learning
A pump is proposed after water enters beside an old wall foundation.
Decision and explanation
Keep people out while a competent person reviews water control, ground movement and the adjoining foundation.
Dewatering can affect ground and structures. It belongs in the protective design and inspection process.
Lesson 11
Atmospheres and confined-space decisions
An open excavation can still contain a dangerous atmosphere. Assessment, equipment and emergency arrangements must match the risk.
When must the team stop entry for atmosphere or rescue risk?
A trench is not automatically a confined space, but poor ventilation, contamination, oxygen deficiency, gas, flooding or difficult escape can make entry dangerous.
Check the actual substances, ground history, nearby services and ventilation. Where a specified confined-space risk exists, use the applicable GB or NI legal route, avoid entry where possible and provide a competent safe system and rescue plan. Never send an unprotected colleague in for an improvised rescue.
Visual practice · Atmospheres and confined-space decisions
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.When must the team stop entry for atmosphere or rescue risk?
A trench is not automatically a confined space, but poor ventilation, contamination, oxygen deficiency, gas, flooding or difficult escape can make entry dangerous. Check the actual substances, ground history, nearby services and ventilation. Where a specified confined-space risk exists, use the applicable GB or NI legal route, avoid entry where possible and provide a competent safe system and rescue plan. Never send an unprotected colleague in for an improvised rescue.
What emergency arrangements are needed for excavation work?
For collapse, flooding, service strike or suspect atmosphere, stop work, keep others out and call the planned emergency response. Do not create another casualty through improvised trench entry. Before entry, confirm rescue access, communications, location information and who controls plant and services during an incident. A narrow pit or unstable face may prevent ordinary first-aid access.
How harm develops in the linked model
Water can erode support and flood the work area. Exhaust, contamination or oxygen depletion can create dangerous atmospheres; an excavation may also meet the confined-space definition.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What emergency arrangements are needed for excavation work?
For collapse, flooding, service strike or suspect atmosphere, stop work, keep others out and call the planned emergency response. Do not create another casualty through improvised trench entry.
Before entry, confirm rescue access, communications, location information and who controls plant and services during an incident. A narrow pit or unstable face may prevent ordinary first-aid access.
After an event, preserve the area, account for workers and obtain competent reassessment before any recovery work or restart.
Emergency scenarios - Emergency scenarios
Scenario
Immediate priority
Planning need
Collapse
Do not create additional casualties.
Rescue plan, emergency services access and support assessment.
Gas strike
Stop work, evacuate and control ignition.
Utility contact and exclusion zone.
Cable strike
Keep clear of live danger and seek emergency help.
Electrical emergency briefing and isolation route.
Flooding
Evacuate and prevent entry.
Water monitoring and pump contingency.
Hazardous atmosphere
Do not enter without controls.
Atmosphere testing, rescue and ventilation plan.
Public interface
Protect public and secure the area.
Barriers, signage and communication plan.
Apply the learning
A deep pit has poor ventilation and a possible contaminated service connection.
Decision and explanation
Assess the atmospheric and confined-space hazards and provide the required safe system before entry.
An open excavation can still contain a dangerous atmosphere. Assessment, equipment and emergency arrangements must match the risk.
Lesson 12
Keep people clear of moving plant
Visibility aids and clothing do not establish separation from the operating envelope or protect an unstable edge.
How should plant and vehicle interface be controlled?
Set plant movements around the opening the crew actually has today. Barriers, banksman arrangements and spoil locations must prevent people being struck and the edge being surcharged.
A delivery, lift or compactor can add a load absent from the original support calculation. Stop its approach until the competent lead confirms the permitted distance and sequence.
The operator should know the service exclusion zone, crossing point and signal to stop. Do not swing a bucket over entrants or let access routes be blocked by vehicles.
One-way routes, reversing controls and visibility.
Service exposure
Bucket damages cables or pipes.
Hand dig or controlled methods near services.
Emergency access
Plant blocks rescue or emergency routes.
Access route kept clear.
Visual practice · Keep people clear of moving plant
Actual SHAREsimulate model capture · A proposed spoil change would load the excavation edge. The exercise description supplies the scenario; a still image cannot establish hidden conditions.How should plant and vehicle interface be controlled?
Set plant movements around the opening the crew actually has today. Barriers, banksman arrangements and spoil locations must prevent people being struck and the edge being surcharged. A delivery, lift or compactor can add a load absent from the original support calculation. Stop its approach until the competent lead confirms the permitted distance and sequence.
How should excavation appear in a risk register?
Record the particular open trench condition: exposed depth and soil, installed support, water, edge loads, services, people entering and the next operation. Assign controls and an owner to each changing hazard. “Excavation inspected” is weak evidence if it does not say which face was inspected, what changed and whether entry was stopped. Use inspection findings, close calls and support defects to update the live register and method.
How harm develops in the linked model
Surcharge and vibration can destabilise the face, while falling spoil or a vehicle can strike people below.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
How should excavation appear in a risk register?
Record the particular open trench condition: exposed depth and soil, installed support, water, edge loads, services, people entering and the next operation.
Assign controls and an owner to each changing hazard. “Excavation inspected” is weak evidence if it does not say which face was inspected, what changed and whether entry was stopped.
Use inspection findings, close calls and support defects to update the live register and method. The record should make the re-entry decision understandable to the next shift.
Support, barriers, access, plant segregation and safe digging.
Trench box, CAT scan, trial holes and barriers.
Owner
Person responsible for control implementation.
Site manager and temporary works supervisor.
Inspection
Competent inspection frequency and triggers.
Start of shift and after rain.
Emergency
Specific response arrangements.
Service strike and collapse plan briefed.
Apply the learning
The operator cannot see a person checking levels beside the bucket and excavation edge.
Decision and explanation
Stop movement and establish a protected arrangement for the person and plant.
Visibility aids and clothing do not establish separation from the operating envelope or protect an unstable edge.
Lesson 13
Inspection is a continuing decision
Inspections must respond to events that can affect safety, not only the calendar. Record defects and the conditions for release.
What inspections are needed for excavations?
A competent person checks the open excavation and its precautions at the start of a working shift and after events that may affect stability, applying the relevant GB or NI rules.
The inspection should cover the exposed face, support or batter, water, edges, access, service protection and nearby loads. Defects need a named owner, exclusion of entry and a recorded correction before release.
A form signed before a crack, flood or plant movement is historical evidence. The observed change controls the next decision; inspect again rather than relying on the earlier tick.
Support, sides, edges, access, water, spoil, services and barriers.
Confirm safe before work starts.
After rain or weather change
Water ingress, erosion, softening and support loading.
Reassess controls.
After collapse or fall of earth
Stability, support damage and need for redesign.
Stop work until safe.
After plant impact
Support, edge loading and service damage.
Inspect and repair.
After design or method change
Whether controls still match the work.
Revise RAMS and permit.
Before re-entry
Whether previous defects have been corrected.
Record close-out.
Visual practice · Inspection is a continuing decision
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.What inspections are needed for excavations?
A competent person checks the open excavation and its precautions at the start of a working shift and after events that may affect stability, applying the relevant GB or NI rules. The inspection should cover the exposed face, support or batter, water, edges, access, service protection and nearby loads. Defects need a named owner, exclusion of entry and a recorded correction before release. A form signed before a crack, flood or plant movement is historical evidence.
What assurance record matters at the open excavation?
A management system should connect the design and permit to daily observation, defect escalation, corrective action and documented release. Official management guidance: HSE Managing for health and safety (HSG65) Audit whether inspection records correspond to the actual face, support and weather; whether changed ground prompted review; and whether workers could stop the job. A procedure or ISO certificate alone does not prove that the trench is safe to enter.
How harm develops in the linked model
Rain, ground loading and changes to support can affect the trench and scaffold bearings together. An earlier signed report or a closed gate is not proof that today’s route and workface are safe.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What assurance record matters at the open excavation?
A management system should connect the design and permit to daily observation, defect escalation, corrective action and documented release.
Audit whether inspection records correspond to the actual face, support and weather; whether changed ground prompted review; and whether workers could stop the job. A procedure or ISO certificate alone does not prove that the trench is safe to enter.
Apply the learning
The morning inspection was satisfactory, then a vehicle struck an edge barrier.
Decision and explanation
Close the affected access and arrange competent inspection and corrective action before reuse.
Inspections must respond to events that can affect safety, not only the calendar. Record defects and the conditions for release.
Lesson 14
Respond to a strike or collapse
Rescue must not create further casualties. Emergency services and the utility need accurate location and hazard information.
What should workers do if a buried service is damaged?
Emergency actions must be briefed before work starts because a strike is not the moment to invent the response. The right action depends on the service: electricity, gas, water, sewer, telecoms or hazardous pipeline. Workers should know who calls the service owner, who controls the area, who stops plant, who prevents re-entry and who reports the incident.
With suspected live electrical damage, people should avoid touching equipment, exposed cable or anyone in contact with electricity until it is safe. With gas, ignition sources should be controlled, people moved away and emergency services or the gas emergency number contacted. With water or sewer damage, the risks include trench flooding, undermining, contamination and confined-space atmospheres.
Near misses matter. A scraped duct, cracked pipe, unexpected service or minor cable damage can become a delayed failure if left unreported.
Electricity. Stop work, keep clear, prevent contact, isolate if competent route exists and contact the network owner/emergency services. Damaged cables can arc, re-energise or remain live.
Gas. Stop work, remove ignition sources if safe, evacuate, call emergency gas response and prevent re-entry. Gas can travel and ignite away from the strike point.
Water. Stop work, leave excavation if flooding or instability develops and contact the service owner. Flooding can collapse ground or trap workers.
Sewer/drain. Stop work, avoid contact, consider contamination and confined-space risk. Sewage can expose workers to pathogens and toxic atmospheres.
Telecoms/fibre. Stop work and contact service owner. Service damage can disrupt emergency communications and critical systems.
Hazardous pipeline. Stop work, evacuate according to the pipeline emergency plan and contact the operator immediately. Contents may be flammable, toxic, pressurised or environmentally harmful.
Visual practice · Respond to a strike or collapse
Actual SHAREsimulate model capture · A service plan is mistaken for proof of clearance. The exercise description supplies the scenario; a still image cannot establish hidden conditions.What should workers do if a buried service is damaged?
Workers should stop work, keep people away, raise the alarm and follow the service-specific emergency plan. See HSE HSG47 avoiding danger from underground services Emergency actions must be briefed before work starts because a strike is not the moment to invent the response. The right action depends on the service: electricity, gas, water, sewer, telecoms or hazardous pipeline. Workers should know who calls the service owner, who controls the area, who stops plant, who prevents re-entry and who reports the incident.
What happens if a cable or pipe is struck or suspected damaged?
Stop work, withdraw people from the danger area without touching the service or plant if electrical contact is possible, prevent ignition or entry into gas accumulation areas, and summon the relevant utility emergency service. Do not attempt an improvised repair or assume an apparently minor scrape is harmless. See HSE HSG47 avoiding danger from underground services The supervisor secures the area, preserves facts and arranges competent utility assessment. Work restarts only after the owner confirms status, the method and permit are revised and the team is rebriefed.
How harm develops in the linked model
Plans, colours and nominal depths cannot prove actual location or identity. A strike may cause arc burns, gas release, flooding or loss of essential services.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What happens if a cable or pipe is struck or suspected damaged?
Stop work, withdraw people from the danger area without touching the service or plant if electrical contact is possible, prevent ignition or entry into gas accumulation areas, and summon the relevant utility emergency service. Do not attempt an improvised repair or assume an apparently minor scrape is harmless. See HSE HSG47 avoiding danger from underground services
The supervisor secures the area, preserves facts and arranges competent utility assessment. Work restarts only after the owner confirms status, the method and permit are revised and the team is rebriefed. Emergency service and evacuation details depend on the asset and site plan.
Apply the learning
A service is damaged and an injured colleague is near the excavation.
Decision and explanation
Stop, keep others clear, raise the alarm and follow the service-specific emergency plan without exposing rescuers.
Rescue must not create further casualties. Emergency services and the utility need accurate location and hazard information.
Lesson 15
Brief the workface and hand over change
The handover must explain the actual state of the excavation and the protective sequence, not simply prove that a briefing took place.
What must the field team be competent to notice?
The site team needs task-specific instruction in the installed support system, service locating, edge and plant exclusion, access, inspection triggers, communication and emergency arrangements.
A competent inspector must understand the ground and support limits and have authority to close the excavation. Plant operators need the permitted approach and spoil locations; entrants need a plain stop-work rule. Brief changed conditions again before re-entry.
Visual practice · Brief the workface and hand over change
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.What must the field team be competent to notice?
The site team needs task-specific instruction in the installed support system, service locating, edge and plant exclusion, access, inspection triggers, communication and emergency arrangements. A competent inspector must understand the ground and support limits and have authority to close the excavation. Plant operators need the permitted approach and spoil locations; entrants need a plain stop-work rule. Brief changed conditions again before re-entry.
What should excavation inspection and handback records establish?
Compare the protected work state with a changed condition, then examine what must be recorded before the ground closes. Inspection findings, measured service evidence and an authorised handback are different records. Check at the start of the shift and after stability-affecting events or a fall of material. Unsafe findings keep work stopped until addressed.
How harm develops in the linked model
Rain, ground loading and changes to support can affect the trench and scaffold bearings together. An earlier signed report or a closed gate is not proof that today’s route and workface are safe.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What should excavation inspection and handback records establish?
Compare the protected work state with a changed condition, then examine what must be recorded before the ground closes. Inspection findings, measured service evidence and an authorised handback are different records.
Educational example, not to scale. Existing services may differ. This view is not a site survey, excavation design or permit to dig.
Inspection and assurance companion; blank sample fields are not completed inspections or company evidence.
A new shift arrives while support is being changed and the inspection record is incomplete.
Decision and explanation
Hold entry and brief the current sequence, restrictions, unresolved defects and release authority.
The handover must explain the actual state of the excavation and the protective sequence, not simply prove that a briefing took place.
Lesson 16
Build an evidence pack
Evidence must connect the planned system to present conditions and resolved defects; volume of paperwork is not assurance.
How would BuildOut Ltd manage a changed open trench?
BuildOut would close entry when an unexpected wet layer and edge crack appear, obtain competent reassessment, correct the support and water controls, then document a fresh hand-back.
BuildOut Ltd is laying a drainage connection beside an occupied building. The pre-dig release covered service location and a support design for the first stage; a crew has installed a trench box and begun entry. Overnight rain brings water through a newly exposed layer. A delivery vehicle is due beside the excavation.
At the start-of-shift check, the inspector sees a crack behind the box and damp material at the toe. The supervisor stops entry, moves the crew and vehicle away from the edge, marks the exclusion zone and tells the site manager and temporary-works lead. The earlier permit remains in the record but cannot override the current observation.
The competent lead checks the actual soil and water path, support contact and box limits, the nearby foundation, vehicle surcharge and escape route. The service locator record is compared with the exposed pipework; any unexpected service is protected and resolved with its owner. Pumping is assessed for possible loss of fines or undermining rather than started by habit.
The revised method may require further support, a different dewatering arrangement or a changed delivery route. BuildOut briefs the groundworkers and operator on the new sequence and confirms that barriers, access and rescue arrangements still work. No one enters to install correction until that activity itself has a safe method.
The inspector records the defect, decision, correction and fresh inspection. The site manager signs a clear hand-back for the defined stage; the crew knows which later changes trigger another stop. At close-out, the team reinstates by a safe support-removal sequence and updates as-built service information.
Visual practice · Build an evidence pack
Actual SHAREsimulate model capture · The excavation inspection no longer matches today’s trench. The exercise description supplies the scenario; a still image cannot establish hidden conditions.How would BuildOut Ltd manage a changed open trench?
BuildOut would close entry when an unexpected wet layer and edge crack appear, obtain competent reassessment, correct the support and water controls, then document a fresh hand-back. BuildOut Ltd is laying a drainage connection beside an occupied building. The pre-dig release covered service location and a support design for the first stage; a crew has installed a trench box and begun entry. Overnight rain brings water through a newly exposed layer.
How should a learner answer a live-trench scenario?
For a NEBOSH Construction excavation scenario, start with the condition found at the workface and the immediate decision: exclude entry, protect others and obtain a competent reassessment. Then explain the causal chain—ground or water change, failed support or edge load, people exposed—and specify physical controls, inspection evidence and safe hand-back. Avoid a generic answer that lists “PPE, training and signs” without preventing collapse or service contact.
How harm develops in the linked model
Rain, ground loading and changes to support can affect the trench and scaffold bearings together. An earlier signed report or a closed gate is not proof that today’s route and workface are safe.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
Field decision: withdraw, correct and re-open
Task, material and setting: Drainage trench in layered wet ground beside an occupied building and delivery route.
People and prerequisites: Groundworkers, operator and occupants; approved support method, service information and competent inspector available.
Before: Inspect the open face and installed box; move vehicle and crew away from the edge.
During: Stop entry on the crack and water; reassess support, drainage, foundation and service exposure.
Hold or stop: Do not enter or pump by assumption while the changed ground and safe correction method are unresolved.
Completion and hand-back: Verify corrected support, access and water control; brief the crew and record a fresh release.
How should a learner answer a live-trench scenario?
For a NEBOSH Construction excavation scenario, start with the condition found at the workface and the immediate decision: exclude entry, protect others and obtain a competent reassessment.
Then explain the causal chain—ground or water change, failed support or edge load, people exposed—and specify physical controls, inspection evidence and safe hand-back. Avoid a generic answer that lists “PPE, training and signs” without preventing collapse or service contact.
Apply the learning
A review finds signed forms but no link between the support drawing, installation and changed edge loading.
Decision and explanation
Trace the current design, installed controls, inspection findings and actions to the specific workface.
Evidence must connect the planned system to present conditions and resolved defects; volume of paperwork is not assurance.
Lesson 17
Capstone: earn a controlled restart
A restart is a coordinated decision based on all relevant conditions, not one repaired symptom.
What should excavation inspection and handback records establish?
Compare the protected work state with a changed condition, then examine what must be recorded before the ground closes. Inspection findings, measured service evidence and an authorised handback are different records.
Educational example, not to scale. Existing services may differ. This view is not a site survey, excavation design or permit to dig.
Inspection and assurance companion; blank sample fields are not completed inspections or company evidence.
Visual practice · Capstone: earn a controlled restart
SHAREhub photographic illustration · Protected UK excavation with trench support and barriers. Use the written case for the exercise; this image does not prove a defect or safe system.What should excavation inspection and handback records establish?
Compare the protected work state with a changed condition, then examine what must be recorded before the ground closes. Inspection findings, measured service evidence and an authorised handback are different records. Check at the start of the shift and after stability-affecting events or a fall of material. Unsafe findings keep work stopped until addressed.
What must be confirmed before anyone enters an excavation?
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release. Keep people out when any of those controls is uncertain. CAT and Genny are service-locating aids, not proof that the trench is clear. Keep the plans, locator record and safe-exposure method at the workface; the supervisor must reconcile any new indication before digging continues.
How harm develops in the linked model
Ground can collapse suddenly and bury or crush a person. A trench box protects only when correctly selected, installed and used within its designed arrangement.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What must be confirmed before anyone enters an excavation?
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release. Keep people out when any of those controls is uncertain.
Best-practice guide · six simple steps
Best-practice guide: Excavations: ground, services and inspection
Start with the key actions, then explore value, a workplace example, harm, stronger controls and further help. Choose a step or use Previous and Next; the guide does not advance automatically.
Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links.
Read all six steps as text
1. What must be confirmed before anyone enters an excavation?
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release.
Control the task: Locate, mark, expose and protect services before digging.
Verify before release: Excavation decision record.
Entry is a fresh workface decision: inspect the actual face and installed support, check services, water, edge loads and access, then record a competent release. Keep people out when any of those controls is uncertain. An open excavation can fail without warning when soil, water, support, edge loads or vibration change.
Apply it: Which part of this plan would you check at the workface before authorising the task?
An open excavation can fail without warning when soil, water, support, edge loads or vibration change. Before entry and after each relevant change, a competent person must verify the actual support or site-specific batter, safe access, buried services, plant separation and rescue arrangements. Inspection observations, photographs, temporary-works decision, revised method, briefing and hand-back log.
Apply it: What evidence would show that the change improves this task, rather than only completing a record?
Fictional example: a practical application of the existing topic lesson.
Setting: Drainage trench in layered wet ground beside an occupied building and delivery route.
Act: Inspect the open face and installed box; move vehicle and crew away from the edge.
Hold / review: Do not enter or pump by assumption while the changed ground and safe correction method are unresolved.
Stop entry on the crack and water; reassess support, drainage, foundation and service exposure. Verify corrected support, access and water control; brief the crew and record a fresh release.
Apply it: At which point would you hold this example, and what evidence would allow it to proceed?
Connect the task, the route to the person and the control that can fail.
Source / exposure: Scan the face, base, edges, access and nearby activities together: collapse, falling people or material, buried services, vehicles, water and hazardous atmospheres can interact.
Possible consequence: A displaced support strut, fresh fissure, saturated layer, unstable spoil, unguarded edge or restricted escape route is a live stop-work signal.
Control failure: The inspector records the change, keeps people clear and gets the support or sequence reassessed before re-entry.
Scan the face, base, edges, access and nearby activities together: collapse, falling people or material, buried services, vehicles, water and hazardous atmospheres can interact.
Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby?
Collapse and engulfment: Control ground movement, edge loading, support, battering or shoring.
Buried services: Locate, mark, expose and protect services before digging.
Water ingress: Assess groundwater, rain, flooding, pumps and emergency escape.
Plant interface: Separate excavations from plant, spoil, lifting and vehicle movement.
Decision tree: Decide whether excavation needs design, temporary works, permit-to-dig or specialist support. Collapse and engulfment: Control ground movement, edge loading, support, battering or shoring. Buried services: Locate, mark, expose and protect services before digging. Water ingress: Assess groundwater, rain, flooding, pumps and emergency escape. Plant interface: Separate excavations from plant, spoil, lifting and vehicle movement. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged.
Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk?
Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status.
Apply it: Which official source and full-topic section will you use to resolve the next decision?
Simplified learning guide. Use the full topic, current official guidance and the actual work arrangements. Workplace scenarios labelled fictional are illustrative examples.
CAT and Genny are service-locating aids, not proof that the trench is clear. Keep the plans, locator record and safe-exposure method at the workface; the supervisor must reconcile any new indication before digging continues.
At a wet pit beside a wall, close access while a competent lead checks whether the wall foundation and temporary support still satisfy the design. Re-open only after the revised sequence, water control and traffic set-back are briefed and verified.
Control ground movement, edge loading, support, battering or shoring.
Design or inspection record.
Buried services
Locate, mark, expose and protect services before digging.
Plans, CAT/Genny checks and trial holes.
Water ingress
Assess groundwater, rain, flooding, pumps and emergency escape.
Inspection and weather review.
Plant interface
Separate excavations from plant, spoil, lifting and vehicle movement.
Traffic and exclusion plan.
Stop-work triggers
Cracks, water, unsupported sides, unmarked services or changed ground stop the job.
Stop-work and review log.
Rescue warning
Do not improvise trench rescue; call emergency services and protect others from entering.
Emergency briefing.
Apply the learning
Rain, a route change and a service discrepancy occur together on the fictional Canal Yard project.
Decision and explanation
Keep entry on hold until competent reviews resolve the interacting changes and the revised controls are verified and briefed.
A restart is a coordinated decision based on all relevant conditions, not one repaired symptom.
Lesson 18
Transfer the learning to your next job
Learning helps you ask and verify the right questions; it does not establish specialist design competence or authorise entry.
How does the hierarchy guide a changing workface?
The original design should remove or reduce excavation where practicable. At the open trench, isolation, suitable support, safe access and competent inspection carry the main protection.
Separate plant and people, keep spoil clear, verify support or a site-specific stable batter, and pause entry when any barrier fails. PPE may limit residual injury but cannot hold back a collapsing face. The supervisor records the defect, owner, corrective action and release decision.
Visual practice · Transfer the learning to your next job
Actual SHAREsimulate model capture · The excavation inspection no longer matches today’s trench. The exercise description supplies the scenario; a still image cannot establish hidden conditions.How does the hierarchy guide a changing workface?
The original design should remove or reduce excavation where practicable. At the open trench, isolation, suitable support, safe access and competent inspection carry the main protection. Separate plant and people, keep spoil clear, verify support or a site-specific stable batter, and pause entry when any barrier fails. PPE may limit residual injury but cannot hold back a collapsing face.
What legal duties apply to excavation work?
For a live site, use the GB or NI construction instrument that applies to its nation. The duty is to maintain precautions and inspect support or batter at the required times; a prior design does not excuse unsafe field conditions. Apply confined-space law only when the actual specified risk is present. Keep the jurisdiction, inspector, observations and release evidence traceable to the workface.
How harm develops in the linked model
Rain, ground loading and changes to support can affect the trench and scaffold bearings together. An earlier signed report or a closed gate is not proof that today’s route and workface are safe.
Try the optional visual exercise in the interactive course, then complete the required lesson decision.
What legal duties apply to excavation work?
For a live site, use the GB or NI construction instrument that applies to its nation. The duty is to maintain precautions and inspect support or batter at the required times; a prior design does not excuse unsafe field conditions.
Apply confined-space law only when the actual specified risk is present. Keep the jurisdiction, inspector, observations and release evidence traceable to the workface.