CDM project mobilisation and coordination procedure

BOUK-PRO-CDM · v1.0 · Completed fictional example · DOCX

Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PRO-CDM | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.

Scope and operating responsibility

We apply this procedure to Retail fit-out with several trades. Evidence includes Appointment and capability checks; pre-construction information; construction phase plan; coordination minutes; design-change and handover records. The role controlling the task checks applicability before mobilisation and whenever the scope changes.

RoleRequired action
Project managerOwn this arrangement, confirm competent support and maintain its evidence trail.
Project manager and Site managerCoordinate the actual package, provide resources and verify prerequisites before release; resolve occupied and subcontractor interfaces.
Trade supervisor and workersUse the accepted current method, demonstrate understanding, report changes and stop when critical safeguards are uncertain.
Competent specialist and H&S adviserProvide technical advice within competence; challenge evidence and identify limitations. Management retains the operating decision.

Inputs before using the procedure

Use the current project risk register, relevant survey and design revisions, equipment or product information, worker consultation and the task-specific records listed below. Resolve conflicting or missing information before relying on it. Do not fill missing technical values from an example.

How we carry out the arrangement

1 Plan and obtain reliable information

For every job the Project Manager records who is client, designer, principal designer, principal contractor and contractor as applicable. Build Out accepts only the roles actually appointed and within its organisational capability.

2 Verify capability and prerequisites

Pre-construction information, design risks, asbestos information, services, access and occupied-building constraints are reviewed before the construction phase plan and package methods are released.

3 Control work and interfaces

The whole project is considered when deciding whether more than one contractor is involved, including sequential trades. Notification, building-control duties and the construction phase plan are distinct decisions; one does not substitute for another.

4 Review change and safe handback

Work-front reviews coordinate subcontractors and design changes, keep welfare and public separation effective, and pass necessary residual information into handover and the health and safety file where required.

Stop restrict and restart

Do not start construction without an adequate project-specific plan, confirmed dutyholder arrangements and the information and resources necessary for safe delivery.

The person controlling the work makes the affected area safe and notifies the Site Manager. Restart requires the competent technical decision for the actual control, the authorised work-release decision and a fresh briefing of affected people. Record unresolved limits; an updated date or a completed form does not remove a hold.

Practical control detail

Client information, design coordination and construction-phase planning form a connected route. Notification is a separate check, rather than permission to start unsafe work.

A useful small-job plan connects people, sequence, controls, welfare and emergency access to the actual site. Update it when conditions change.

Evidence follow up and learning

Worked decision trail

Fictional situationDecision and evidence
What changesHarbour retail fit out shares escape routes with an occupied trading area.
ResponseThe Project Manager agrees phased segregation and escape arrangements with the client before ceiling works start. Notification is assessed separately.
VerificationWalk the route during the planned evening shift and reconcile the CPP with the current trade sequence.

Supporting arrangement documents

ReferenceHow the document is used
BOUK-CHK-CDM-01
Project CDM applicability and dutyholder checklist
Check project definition, client type, contractor count, appointments and notification threshold.
BOUK-REG-CDM-01
Pre-construction information and gap register
Track asbestos, services, design, client and existing-structure information gaps.
BOUK-PLN-CDM-01
Construction phase plan
Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.
BOUK-FRM-CDM-01
F10 notification decision and submission record
Record threshold assessment, responsible dutyholder and update/submission evidence when required.
BOUK-FRM-CDM-02
Coordination meeting and interface action record
Record trade sequencing, shared risks, access and responsibilities.
BOUK-CHK-CDM-02
Health and safety file and handover checklist
Gather proportionate residual-risk information and agree file responsibilities and delivery.

Retain the record ID, task, location, competent author, revision, date, decision, restrictions, action owner and separate effectiveness evidence. Restrict personal and health information and apply the relevant retention rule. File genuine results separately from teaching examples.

Guidance What are the Construction Design and Management Regulations? · What should a construction phase plan include?

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.